Malappuram Sn AE 1 |
Date: 02/07/2024 |
Work in progress | 44% Completed
Side wall completed and plastering work in progress for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities peg marked location for 7.00 LL OHSR for HL zone and hence, intimation given to contractor for submitting design.
Malappuram Sn AE 1 |
Date: 24/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift concrete completed and plastering work in progress for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 20/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift concrete completed for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 14/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift shuttering in progress. Side wall concreting 3rd lift completed for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 05/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift shuttering in progress. Side wall concreting 3rd lift completed for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 22/05/2024 |
Work in progress | 44% Completed
Side wall 4th lift shuttering in progress. Side wall concreting 3rd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 13/05/2024 |
Work in progress | 44% Completed
Side wall concreting 3rd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 30/04/2024 |
Work in progress | 44% Completed
Side wall concreting 3rd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 23/04/2024 |
Work in progress | 44% Completed
Side wall concreting 2nd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started.
Malappuram Sn AE 1 |
Date: 18/04/2024 |
Work in progress | 44% Completed
Side wall concreting first lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 08/04/2024 |
Work in progress | 43% Completed
Side wall shuttering and reinforcement work of 16 LL tank in progress at Kalanparamba. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 04/04/2024 |
Work in progress | 43% Completed
Side wall shuttering and reinforcement work of 16 LL tank in progress at Kalanparamba. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 26/03/2024 |
Work in progress | 42% Completed
Haunch concrete completed for 16LL tank at Kalanparamba. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 22/03/2024 |
Work in progress | 42% Completed
Haunch concrete completed for 16LL tank at Kalanparamba. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 13/03/2024 |
Work in progress | 41% Completed
Columns above deck slab concrete completed. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 07/03/2024 |
Work in progress | 41% Completed
Columns above deck slab concrete completed. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 01/03/2024 |
Work in progress | 41% Completed
Columns above deck slab of 16 LL tank partially complete. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 27/02/2024 |
Work in progress | 40% Completed
Columns above deck slab of 16 LL tank partially complete. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 23/02/2024 |
Work in progress | 39% Completed
Columns above deck slab of 16 LL tank partially complete. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 19/02/2024 |
Work in progress | 39% Completed
Columns above deck slab of 16 LL tank partially complete. Pump house work nearing completion. Work not started to 7 LL tank.
Malappuram Sn AE 1 |
Date: 13/02/2024 |
Work in progress | 38% Completed
Deck slab of 16LL tank concreting completed. Pump house work nearing completion. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 06/02/2024 |
Work in progress | 37% Completed
Deck slab of 16LL tank concreting completed. Pump house work nearing completion. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 02/02/2024 |
Work in progress | 37% Completed
Deck slab of 16LL tank concreting completed. Pump house work nearing completion. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 27/01/2024 |
Work in progress | 36% Completed
Deck slab concreting for 16LL tank started on 25/01/24 and completed on 26/01/24 evening. Pump house work nearing completion. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 22/01/2024 |
Work in progress | 33% Completed
Steel work for base slab in progress for 16LL tank, concreting in two days. Pump house work nearing completion. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 16/01/2024 |
Work in progress | 33% Completed
Shuttering of deck slab in progress for 16LL tank. Pump house work nearing completion. Plastering work and shutter fixed for pump house. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 08/01/2024 |
Work in progress | 31% Completed
Shuttering of deck slab in progress for 16LL tank. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 29/12/2023 |
Work in progress | 30% Completed
Shuttering of deck slab in progress for 16LL tank. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 23/12/2023 |
Work in progress | 29% Completed
The plastering work progressing. Concreting of roof slab completed . The concreting of final length of columns completed in 16 LL Tank. Shuttering of deck slab in progress for 16LL tank. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 19/12/2023 |
Work in progress | 29% Completed
The plastering work progressing. Concreting of roof slab completed . The concreting of final length of columns completed in 16 LL Tank. Shuttering of deck slab in progress. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 13/12/2023 |
Work in progress | 28% Completed
The plastering work progressing. Concreting of roof slab completed . The concreting of final length of columns is progressing in 16 LL Tank. Work not started to 7 LL tank since the land peg marked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 07/12/2023 |
Work in progress | 27% Completed
The plastering work progressing. Concreting of roof slab completed . The concreting of final length of columns is progressing in 16 LL Tank. Work not started to 7 LL tank since the land pegmarked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 30/11/2023 |
Work in progress | 26% Completed
The plastering work progressing. Concreting of roof slab completed . The concreting of columns above fourth brace beam is completed in the 16 LL Tank and concreting of beam completed. Work not started to 7 LL tank since the land pegmarked by panchayat is now not feasible because the surroundings of the land cut down drastically for laterite quarry works. Letter submitted to panchayath for obtaining suitable land satisfying the hydraulic parameters and nearing to the existing land.
Malappuram Sn AE 1 |
Date: 25/11/2023 |
Work in progress | 25% Completed
The masonry work completed for the pump house. The plastering work progressing. Concreting of roof slab completed . The concreting of columns above fourth brace beam is completed in the 16 LL Tank and concreting of beam completed. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet been completed . Letter submitted to panchayath for speeding up this process.
Malappuram Sn AE 1 |
Date: 21/11/2023 |
Work in progress | 24% Completed
The masonry work completed for the pump house. The plastering work progressing. Concreting of roof slab completed . The concreting of columns above fourth brace beam is completed in the 16 LL Tank and concreting of beam is progressing. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet been completed . Letter submitted to panchayath for speeding up this process.
Malappuram Sn AE 1 |
Date: 14/11/2023 |
Work in progress | 23% Completed
The masonry work completed for the pump house. The plastering work progressing. Shuttering of roof slab completed and concreting scheduled for tomorrow. The concreting of columns above fourth brace beam is completed in the 16 LL Tank and concreting of beam is progressing. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet been completed . Letter submitted to panchayath for speeding up this process.
Malappuram Sn AE 1 |
Date: 06/11/2023 |
Work in progress | 22% Completed
The masonry work nearing completion for the pump house. The plastering work progressing. The concreting of columns above fourth brace beam is in progress in the 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet been completed . Letter submitted to panchayath for speed up this process.
Malappuram Sn AE 1 |
Date: 27/10/2023 |
Work in progress | 21% Completed
The masonry work nearing completion for the pump house. The plastering work progressing. The concreting of columns above third brace beam completed in 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet completed . Letter submitted to panchayath for speed up this process
Malappuram PH Dn EE |
Date: 05/10/2023 |
Work in progress | 20% Completed
The masonry work progressing for the pum house. The plastering work progressing. The concreting of third brace beam completed in 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet completed . Letter submitted to panchayath for speed up this process
Malappuram Sn AE 1 |
Date: 25/09/2023 |
Work in progress | 14% Completed
The masonry work progressing for the pum house. The platering work on steining is progressing. The centring work for third brace beam started to 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath.
Malappuram Sn AE 1 |
Date: 16/09/2023 |
Work in progress | 14% Completed
The masonry works for the pump house reached up to the lintel level. The columns of OHSR reached up to 7.00 m.
Malappuram Sn AE 1 |
Date: 11/09/2023 |
Malappuram Sn AE 1 |
Date: 30/08/2023 |
Work in progress | 13% Completed
The concreting of the floor slab, and approach bridge of the well are completed. The columns above the well is in progress. The concreting of 1st overhead brace beams are progressing. Land handed over by the panchayath for constructing 7.00 OHSR at Vattapparambu is insufficient and Panchayath president being try to avail balance land needed.
Malappuram Sn AE 1 |
Date: 18/08/2023 |
Work in progress | 12% Completed
The shuttering work and reinforcement works at NK padi is in good progress, The deck slab cum approach bridge would materialized soon. The centering work of the first over head brace of 16.00 LL is started. The land for OHSR at Vattapparmbu was obtained, but due to its topography and shape, land is insufficient to comfortably accommodate 7.00 LL. An additional 100 Sq.m asked to Panchayath and will obtained soon, the paperwork is in the pipeline at the Panchayath office.
Malappuram Sn AE 1 |
Date: 24/07/2023 |
Work in progress | 11% Completed
The full area required for the Vattapparambu tank has not been handed over by the Panchayath. The concreting of the plinth brace of a portion of Kalamparambu tank was completed. The approach bridge is in progress.
Malappuram Sn AE 1 |
Date: 17/07/2023 |
Work in progress | 10% Completed
Intake well work reached near the subfloor level and the subfloor level slab of the approach bridge was completed. The Kalalanprambu tank work reached up to the plinth level.
Malappuram Sn AE 1 |
Date: 10/07/2023 |
Work in progress | 10% Completed
Site leveling of Vattapparambu tank completed. The footing concrete of Kalanparambu tank progressing. The side protection work of the intake structure is also in progress.
Malappuram Sn AE 1 |
Date: 30/06/2023 |
Work in progress | 10% Completed
Site levelling of Vattapparambu tank completd. The footing concrete of Kalanparambu tank progressing. The side protection work of intake structure also in progress.
Malappuram PH Dn EE |
Date: 26/06/2023 |
Work in progress | 9% Completed
Site levelling
Malappuram Sn AE 1 |
Date: 22/06/2023 |
Work in progress | 8% Completed
2nd brace with pipe supporting slab of the approach bridge is ongoing. The Reinforcement of the RCC footing of OHSR Kalanparambu is progressing and footing concreting is in progress. The land for OHSR Vattapparambu has peg marked by Panchayath and the work can starts soon.
Malappuram Sn AE 1 |
Date: 18/06/2023 |
Work in progress | 8% Completed
1st brace beam work of the approach bridge has been completed and the support columns rising. The Reinforcement of the RCC footing of OHSR Kalanparambu is progressing and footing concreting is in progress. . The land for OHSR Vattapparambu is not started yet because the handing over of land to KWA is still in procedure at Panchayath.
Malappuram Sn AE 1 |
Date: 09/06/2023 |
Work in progress | 8% Completed
The concreting of 1st brace beam work of the approach bridge has completed and the support columns rising. The Reinforcement of the RCC footing of OHSR Kalanparambu is progressing. The land for OHSR Vattapparambu is not started yet because the handing over of land to KWA is still in procedure at Panchayath.
Malappuram Sn AE 1 |
Date: 06/06/2023 |
Work in progress | 7% Completed
The concreting of brace beam work of the approach bridge of the well is scheduled to tomorrow
Malappuram Sn AE 1 |
Date: 01/06/2023 |
Work in progress | 7% Completed
The brace beam work of the approach bridge of the well is progressing. The bottom PCC work progressing.
Malappuram Sn AE 1 |
Date: 27/05/2023 |
Work in progress | 7% Completed
Surroundings of well filled with red earth and brace work of the approach bridge started. The PCC concreting of the tank at Kalanparambu started. No decision taken yet to avail a department vehicle for transporting to site
Malappuram Sn AE 1 |
Date: 24/05/2023 |
Work in progress | 7% Completed
Surroundings of well filled with red earth. The supervision of work facing much hard due to lack of dept.Vehicle
Malappuram PH Dn EE |
Date: 23/05/2023 |
Work in progress | 7% Completed
The work of approch bridge to the well is in progress. The Earth work of OHSR at Kalanparambu has completed and PCC concrete will starts soon.
Malappuram Sn AE 1 |
Date: 20/05/2023 |
Work in progress | 7% Completed
The work of approch bridge to the well is in progress. The Earth work of OHSR at Kalanparambu has completed and PCC concrete will starts soon.
Malappuram PH Dn EE |
Date: 19/05/2023 |
Work in progress | 7% Completed
Work of approach bridge -footing completed. Earth work completed for OHSR at Kalamparambu . Column work in progress
Malappuram PH Dn EE |
Date: 16/05/2023 |
Work in progress | 7% Completed
Work of approach bridge -footing completed. Earth work completed for OHSR at Kalamparambu .
Malappuram PH Dn EE |
Date: 09/05/2023 |
Work in progress | 7% Completed
Work of approach bridge started.
Malappuram Sn AE 1 |
Date: 03/05/2023 |
Work in progress | 7% Completed
The sub floor of well concrete completed.
Malappuram Sn AE 1 |
Date: 27/04/2023 |
Work in progress | 7% Completed
steining completed upto the subfloor height. Side protection work proceeding
Malappuram PH Dn EE |
Date: 24/04/2023 |
Work in progress | 7% Completed
Steining upto subfloor has completed. The RR retaining work is in progress.
Malappuram Sn AE 1 |
Date: 17/04/2023 |
Work in progress | 7% Completed
Well steining 7.20 m completed, Leading chanel completed. SRR side side protection progressing. 16.00 LL OHSR setting out completed.
Malappuram Sn AE 1 |
Date: 13/04/2023 |
Work in progress | 7% Completed
One part bill submitted. Facing many problems to supervise the work by cancellation the registration of Department's Vehicle
Malappuram Sn AE 1 |
Date: 07/04/2023 |
Work in progress | 6% Completed
Steining concrete above 7 m and cover slab of leading chanal complete.
Malappuram Sn AE 1 |
Date: 04/04/2023 |
Work in progress | 5% Completed
Shuttering work of the intake channel cover slab and steining above 7m is progressing
Malappuram Sn AE 1 |
Date: 31/03/2023 |
Work in progress | 5% Completed
Last lap of intake channel - cover slab in progressing. Setting out done to OHSR Kalanparambu.
Malappuram PH Dn EE |
Date: 22/03/2023 |
Work in progress | 5% Completed
The concreting of steining upto 7.20 m will completed. intake channel work completed.. site leveling work ongoing at the WTP and OHSR site for setting out the tank.
Malappuram Sn AE 1 |
Date: 14/03/2023 |
Work in progress | 5% Completed
The concreting of steining upto 7.20 m will complete tomorrow. Instruct to level the WTP and OHSR site for setting out the tank
Malappuram Sn AE 1 |
Date: 07/03/2023 |
Work in progress | 5% Completed
First lift of intake chanel concrete completed today. The OHSR for LL zone will start next week.
Malappuram Sn AE 1 |
Date: 28/02/2023 |
Work in progress | 5% Completed
The PCC work of intake chanel completed. Works progressing
Malappuram Sn AE 1 |
Date: 14/02/2023 |
Work in progress | 4% Completed
Well steining work in progress
Malappuram Sn AE 1 |
Date: 09/02/2023 |
Work in progress | 2% Completed
The steining concrete completed up to 2.4m from bottom plug
Malappuram PH Dn EE |
Date: 19/01/2023 |
Work in progress | 0% Completed
The earth work for the well will start in 2 days ,
Malappuram Sn AE 1 |
Date: 29/12/2022 |
Work has started | 0% Completed
Joint inspection conducted with contractor's staff and instruction given to start the work.