Project | JJM-WSS to Ayarkunnam Panchayath Package 2 |
---|---|
Project Code | KTMJJM12206034P2 |
Type | Package |
Main Project | JJM-WSS to Ayarkunnam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Package 2-Supplying and erection of raw water pump set , interconnection works of raw water pumping main, providing indoor type transformer at WTP, construction of transformer room and providing FHTCs in Zone 1(Z 1 ) |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 15600000 |
TS Number | 736/2020-21 |
Technical specification | Package 2-Supplying and erection of raw water pump set , interconnection works of raw water pumping main, providing indoor type transformer at WTP, construction of transformer room and providing FHTCs in Zone 1(Z 1 ) |
Contractor | RAJU KARUKACHERIL JOSEPH (Mob: 9447153677) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 05 Jul 2021 |
Expected date of Completion | 31/10/2022 |
TS Date | 31 Dec 2020 |
---|---|
Estimate Approval | 29 Dec 2020 |
NIT Approval | 01 Jan 2021 |
Tender Closing | 12 Jan 2021 |
Technichal Pre-Qualification | 21 Jan 2021 |
Price bid opening | 28 Jan 2021 |
Workorder Date | 04 Feb 2021 |
---|---|
NA | 16 Feb 2021 |
Kottayam Proj Dn AE4 |
Date: 26/06/2024 |
Work in progress | 57% Completed
Letter was issued to contractor on 25.3.24 to intimate the detailes of supply urgently.The contractor ensured to supply pumpset before 30.4.24.Tille date the contractor had not supplied .Hence final notice was issued to contractor on 29.5.24 View all updates .
Kottayam Proj Dn AE4 |
Date: 25/06/2024 |
Work in progress | 57% Completed
Letter was issued to contractor on 25.3.24 to intimate the detailes of supply urgently.The contractor ensured to supply pumpset before 30.4.24.Tille date the contractor had not supplied .Hence final notice was issued to contractor on 29.5.24 View all updates .