Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-WSS to Ayarkunnam Panchayath Package 2

Project JJM-WSS to Ayarkunnam Panchayath Package 2
Project Code KTMJJM12206034P2
Type Package
Main Project JJM-WSS to Ayarkunnam Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Package 2-Supplying and erection of raw water pump set , interconnection works of raw water pumping main, providing indoor type transformer at WTP, construction of transformer room and providing FHTCs in Zone 1(Z 1 )
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 15600000
TS Number 736/2020-21
Technical specification Package 2-Supplying and erection of raw water pump set , interconnection works of raw water pumping main, providing indoor type transformer at WTP, construction of transformer room and providing FHTCs in Zone 1(Z 1 )
Contractor RAJU KARUKACHERIL JOSEPH (Mob: 9447153677)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/02/2021
Scheduled date of Completion as per agreement 05 Jul 2021
Expected date of Completion 31/10/2022

Processing Dates

TS Date 31 Dec 2020
Estimate Approval 29 Dec 2020
NIT Approval 01 Jan 2021
Tender Closing 12 Jan 2021
Technichal Pre-Qualification 21 Jan 2021
Price bid opening 28 Jan 2021

Approval Dates

Workorder Date 04 Feb 2021
NA 16 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 26/06/2024

Work in progress | 57% Completed

Letter was issued to contractor on 25.3.24 to intimate the detailes of supply urgently.The contractor ensured to supply pumpset before 30.4.24.Tille date the contractor had not supplied .Hence final notice was issued to contractor on 29.5.24 View all updates .

Kottayam Proj Dn AE4
Date: 25/06/2024

Work in progress | 57% Completed

Letter was issued to contractor on 25.3.24 to intimate the detailes of supply urgently.The contractor ensured to supply pumpset before 30.4.24.Tille date the contractor had not supplied .Hence final notice was issued to contractor on 29.5.24 View all updates .