Project | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation |
---|---|
Project Code | TCRJJM07203874P2 |
Type | Package |
Main Project | JAL JEEVAN MISSION 2020-21- THRIKKUR GRAMA PANCHAYATH - Providing FHTC to Rural house holds, Retrofitting , Augmentation of Existing Rural Water Supply Schemes |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM Thrikkur panchayath 2020-21 - App:12 B & 12 E-pipeline extension to various wards and providing WSC after augmentation |
Status | On-going |
District | Thrissur |
Executing Office | Ollur Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 46200000 |
TS Number | TS/2020-2021/2020/13451 |
Technical specification | 800 Nos FHTC |
Contractor | Litty George (Mob: 8850167071) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/03/2021 |
---|---|
Scheduled date of Completion as per agreement | 07 Sep 2021 |
Expected date of Completion | 31/12/2022 |
TS Date | 05 Sep 2020 |
---|---|
Estimate Approval | 05 Sep 2020 |
NIT Approval | 25 Feb 2021 |
Tender Closing | 05 Mar 2021 |
Technichal Pre-Qualification | 05 Mar 2021 |
Price bid opening | 05 Mar 2021 |
Workorder Date | 27 May 2021 |
---|---|
NA | 05 Jul 2021 |
Ollur AE |
Date: 30/04/2024 |
Work has been completed | 100% Completed
CC 9 th and Final bill submitted to Division office on 07/07/2023.
Ollur AE |
Date: 06/04/2024 |
Work has been completed | 100% Completed
CC 9 th and Final bill submitted to Division office on 07/07/2023.