| Project | AMRUT-1.0--Kozhikode Water Supply project-Replacing old and damged pipes at Electoral ward 10 and Providing FHTCs -Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P54 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0--Kozhikode Water Supply project-Replacing old and damged pipes at Electoral ward 10 and Providing FHTCs -Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 2 Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 13500000 |
| TS Number | 14585/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/02/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Mar 2024 |
| Expected date of Completion | 31/07/2024 |
| TS Date | 21 Sep 2023 |
|---|---|
| Estimate Approval | 21 Sep 2023 |
| NA | 08 Sep 2023 |
|---|
| Kozhikode PH Dn EE |
| Date: 30/10/2024 |
Work has been completed | 100% Completed
Work in completed. Pipe laid-2.353km, FHTCs-378 nos.
| Kozhikode PH Dn EE |
| Date: 24/10/2024 |
Work in progress | 98% Completed
Work in progress. Pipe laid-2.353km, FHTCs-353. Restoration work in progress.