| Kozhikode PH Dn EE |
| Date: 30/10/2024 |
Work has been completed | 100% Completed
Work in completed. Pipe laid-2.353km, FHTCs-378 nos
| Kozhikode PH Dn EE |
| Date: 24/10/2024 |
Work in progress | 98% Completed
Work in progress. Pipe laid-2.353km, FHTCs-353. Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 23/10/2024 |
Work in progress | 98% Completed
Work in progress. Pipe laid-2.353km, FHTCs-353. Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 22/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started
| Kozhikode PH Dn EE |
| Date: 19/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started
| Kozhikode PH Dn EE |
| Date: 18/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started
| Kozhikode PH Dn EE |
| Date: 17/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 16/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 15/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 12/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 11/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 09/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 08/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 05/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 04/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 01/10/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 28/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 27/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 26/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 25/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 24/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 23/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 19/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 18/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 13/09/2024 |
Work in progress | 96% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 12/09/2024 |
Work in progress | 95% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 11/09/2024 |
Work in progress | 95% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work in progress | 95% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 09/09/2024 |
Work in progress | 95% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 93% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 19/08/2024 |
Work in progress | 93% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work in progress | 93% Completed
Work in progress. Pipe laid-2.353km, FHTCs-305
| Kozhikode PH Dn EE |
| Date: 26/06/2024 |
Work in progress | 90% Completed
Work in progress. Pipe laid-2.353km, FHTCs-255
| Kozhikode PH Dn EE |
| Date: 25/06/2024 |
Work in progress | 90% Completed
Work in progress. Pipe laid-2.353km, FHTCs-255
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 90% Completed
Work in progress. Pipe laid-2.353km, FHTCs-255
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 89% Completed
Work in progress. Pipe laid-110mm PVC-2328.8, FHTCs-255 nos.
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 53% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 33% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 28% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work in progress | 24% Completed
pipe laid 1.02km, FHTCs-85 nos.
| Kozhikode PH Dn EE |
| Date: 04/03/2024 |
Work in progress | 22% Completed
pipe laid 1.02km, FHTCs-85 nos.
| Kozhikode PH Dn EE |
| Date: 03/03/2024 |
Work in progress | 21% Completed
pipe laid 1.02km, FHTCs-85 nos.
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work in progress | 20% Completed
pipe laid 1.02km, FHTCs-85 nos.
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 15% Completed
pipe laid 1.02km, FHTCs-85 nos.
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 12% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work in progress | 9% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work in progress | 9% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 9% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 08/01/2024 |
Work in progress | 6% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 5% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 5% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 5% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/01/2024 |
Work in progress | 5% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 4% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 02/01/2024 |
Work in progress | 4% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 4% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 20/11/2023 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 30/10/2023 |
Work has started | 0% Completed
Site Handed Over