Kozhikode PH Dn EE
Date: 30/10/2024

Work has been completed | 100% Completed

Work in completed. Pipe laid-2.353km, FHTCs-378 nos

Kozhikode PH Dn EE
Date: 24/10/2024

Work in progress | 98% Completed

Work in progress. Pipe laid-2.353km, FHTCs-353. Restoration work in progress

Kozhikode PH Dn EE
Date: 23/10/2024

Work in progress | 98% Completed

Work in progress. Pipe laid-2.353km, FHTCs-353. Restoration work in progress

Kozhikode PH Dn EE
Date: 22/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started

Kozhikode PH Dn EE
Date: 21/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started

Kozhikode PH Dn EE
Date: 19/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started

Kozhikode PH Dn EE
Date: 18/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-349. Restoration work started

Kozhikode PH Dn EE
Date: 17/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 16/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 15/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 14/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 12/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 11/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 10/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 09/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 08/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 07/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 05/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 04/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 03/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 01/10/2024

Work in progress | 97% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 30/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 28/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 27/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 26/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 25/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 24/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 23/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 20/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 19/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 18/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 13/09/2024

Work in progress | 96% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 12/09/2024

Work in progress | 95% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 11/09/2024

Work in progress | 95% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 10/09/2024

Work in progress | 95% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 09/09/2024

Work in progress | 95% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 21/08/2024

Work in progress | 93% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 19/08/2024

Work in progress | 93% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305. Restoration work started

Kozhikode PH Dn EE
Date: 16/08/2024

Work in progress | 93% Completed

Work in progress. Pipe laid-2.353km, FHTCs-305

Kozhikode PH Dn EE
Date: 26/06/2024

Work in progress | 90% Completed

Work in progress. Pipe laid-2.353km, FHTCs-255

Kozhikode PH Dn EE
Date: 25/06/2024

Work in progress | 90% Completed

Work in progress. Pipe laid-2.353km, FHTCs-255

Kozhikode PH Dn EE
Date: 24/06/2024

Work in progress | 90% Completed

Work in progress. Pipe laid-2.353km, FHTCs-255

Kozhikode PH Dn EE
Date: 14/06/2024

Work in progress | 89% Completed

Work in progress. Pipe laid-110mm PVC-2328.8, FHTCs-255 nos.

Kozhikode PH Dn EE
Date: 21/04/2024

Work in progress | 53% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 33% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 28% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 05/03/2024

Work in progress | 24% Completed

pipe laid 1.02km, FHTCs-85 nos.

Kozhikode PH Dn EE
Date: 04/03/2024

Work in progress | 22% Completed

pipe laid 1.02km, FHTCs-85 nos.

Kozhikode PH Dn EE
Date: 03/03/2024

Work in progress | 21% Completed

pipe laid 1.02km, FHTCs-85 nos.

Kozhikode PH Dn EE
Date: 02/03/2024

Work in progress | 20% Completed

pipe laid 1.02km, FHTCs-85 nos.

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 15% Completed

pipe laid 1.02km, FHTCs-85 nos.

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 12% Completed

Work in progress

Kozhikode PH Dn EE
Date: 30/01/2024

Work in progress | 9% Completed

Work in progress

Kozhikode PH Dn EE
Date: 29/01/2024

Work in progress | 9% Completed

Work in progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 9% Completed

Work in progress

Kozhikode PH Dn EE
Date: 08/01/2024

Work in progress | 6% Completed

Work in progress

Kozhikode PH Dn EE
Date: 07/01/2024

Work in progress | 5% Completed

Work in progress

Kozhikode PH Dn EE
Date: 06/01/2024

Work in progress | 5% Completed

Work in progress

Kozhikode PH Dn EE
Date: 05/01/2024

Work in progress | 5% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/01/2024

Work in progress | 5% Completed

Work in progress

Kozhikode PH Dn EE
Date: 03/01/2024

Work in progress | 4% Completed

Work in progress

Kozhikode PH Dn EE
Date: 02/01/2024

Work in progress | 4% Completed

Work in progress

Kozhikode PH Dn EE
Date: 01/01/2024

Work in progress | 4% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work has started | 0% Completed

Supply order placed for pipes

Kozhikode PH Dn EE
Date: 29/11/2023

Work has started | 0% Completed

Supply order placed for pipes

Kozhikode PH Dn EE
Date: 20/11/2023

Work has started | 0% Completed

Supply order placed for pipes

Kozhikode PH Dn EE
Date: 30/10/2023

Work has started | 0% Completed

Site Handed Over