Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Documents & Files

direction for proposing micro-tunnelling on 07/02/2024.

20/02/2024 | File: Approved Letter - Vasoorichira (3).pdf | Download

Letter to RO MoRTH on 31/10/2023

22/01/2024 | File: Letter to MoRTh 31.10.pdf | Download

Letter from PWD NH Division kollam on 18/10/2023

22/01/2024 | File: letter from PWD NH 18.10.23.pdf | Download

Undertaking

22/01/2024 | File: Undertaking.pdf | Download

Letter to the Executive Engineer, NH Roads division kollam on 18/10/2023

22/01/2024 | File: Letter to NH roads 18.10.23.pdf | Download

Letter to RO NH MoRTH on 5/10/2023

22/01/2024 | File: Letter to RO 5.10.23.pdf | Download

Letter from RO on 30/5/2022

22/01/2024 | File: Letter from RO.pdf | Download

MoRTH application History

22/01/2024 | File: MoRTh application History.pdf | Download

Brief history about the project

20/01/2024 | File: Brief history about the project.pdf | Download

Rejection letter from MoRTH

18/01/2024 | File: NH 183 JJM (1).pdf | Download

Letter from Chief Engineer NH, TVM reg submission of MoRTH Sanction

18/01/2024 | File: Submission.pdf | Download

Request for extension of time of completion upto 31/12/2022, submitted to SE.

20/08/2022 | File: proceedings.pdf | Download

Request for extension of time of completion upto 31/12/2022, submitted to SE.

Appeal Against MORTH Sanction Rejection - Video of pending pipe laying stretch from Nanthirickal to Ellampallor Junction (Google Drive Link)

16/06/2022 | File: Google Drive Link.docx | Download

https://drive.google.com/file/d/1YnGS3hxHlXfCKuST8TD_jiAfr9kZmlv3/view?usp=sharing

Appeal Letter Against MORTH Sanction Rejection 1

16/06/2022 | File: Appeal Letter Against MORTH Sanction Rejection 1.pdf | Download

Appeal Letter from E.E Project Division Kollam to D.C.E PIU II dated 06.06.2022

Appeal Letter Against MORTH Sanction Rejection Letter 2

16/06/2022 | File: Appeal Letter Against MORTH Sanction Rejection Letter 2.pdf | Download

MORTH Rejection Letter

Appeal Letter Against MORTH Sanction Rejection - NOC Letters 3

16/06/2022 | File: Appeal Letter Against MORTH Sanction Rejection - NOC Letters 3.pdf | Download

NOC Letters issued from BSNL & KSEB

Proposed Alignment of 1219mm dia pipe line from Nanthirikal to Elampalloor

16/06/2022 | File: ROAD NEW.pdf | Download

KIIFB -AUGMENTATION OF WSS TO KOLLAM COORPORATION Proposed Alignment of 1219mm dia, 10mm thick MS pipe line from Nanthirikal to Elampalloor (Ch 12/648 to 13/700 )in KOLLAM- THENI NH 183

Alignment of Kollam - Theni NH - Pipe laying completed and proposed details

24/02/2022 | File: | Download

work schedule

20/12/2021 | File: | Download

Balance work schedule -

Risk road cutting issue

20/12/2021 | File: | Download

documents uploaded in e-PMG portal

Technical Sanction Document

03/06/2021 | File: Technical_Sanction_Document___kiifbT.S.pdf | Download

Bar chart of work

03/06/2021 | File: Bar chart of KIIFB laying work..xlsx | Download

Bar chart of work

Balance Schedule of Work

08/03/2021 | File: Balance Schedule of Work - KIIFB Kollam Project.xlsx | Download

Laying of Raw Water Pumping main - Balance Schedule of Work

T S No.KWA/CE(SR)/18/2016-17 dated 23/01/2017

15/07/2020 | File: Technical_Sanction_Document_ _kiifbT.S.pdf | Download

T S Amount Rs. 235 Crore.

AWSS To kollam Corporation - Laying raw water Pumping main 1219 mm dia MS pipe from Njankadavu to WTP at Vasoorichira

15/07/2020 | File: SELECTION_NOTICE OF LAYING WORKS.pdf | Download

Selection Notice

AWSS To kollam Corporation - Laying raw water Pumping main 1219 mm dia MS pipe from Njankadavu to WTP at Vasoorichira - A S No. GO(Rt) No.14/2017/WRD dated Thiruvananthapuram 11/01/2017

15/07/2020 | File: KIIFB - AS.pdf | Download

A S No. GO(Rt) No.14/2017/WRD dated Thiruvananthapuram 11/01/2017 A S Amount - Rs.2350000000.00 (Rupees 235 Crore Only)

A S No. A S No. GO(Rt) No.14/2017/WRD dated Thiruvananthapuram 11/01/2017

15/07/2020 | File: Technical_Sanction_Document_ _kiifbT.S.pdf | Download

T S No. KWA / CE (SR) / 18/2016-17 dated 23/01/2017 AS Amount - 235 Crores T S Amount 235 Crores

SELECTION NOTICE

15/07/2020 | File: SELECTION_NOTICE OF LAYING WORKS.pdf | Download

AWSS to Kollam Corporation - laying raw water pumping main 1219 mm dia MS pipe from Nkjanakadavu to WTP at Vasoorichira - Selection Notice No.KWA/PHC/Q/D5 - 2277/2016 part 1 - (KIIFB Phase II) dated 18/05/2018