Project | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi |
---|---|
Project Code | EKMAMRUT0118684 |
Type | Main project |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi |
Status | On-going |
District | Ernakulam |
Executing Office | Kochi Project Division |
AS Amount (Rs) | 165200000 |
AS Number | GO(Rt)No.5/2018/LSGD dtd 01/01/2018 |
TS Amount (Rs) | 137000000 |
TS Number | ORDER No. TS - CE/CR/KWA/71/17-18 dated 08.02.2018 |
Total Bill Submitted (Rs) | 109833701 |
Total Bill Paid (Rs) | 109833701 |
Population Benefitted | 32000 |
Capacity in MLD | 5.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Kochi corporation division numbers 63,54,62,66 and 67 |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi | Kochi Project Division | |
2 | AMRUT- Rejuvenation of Elamkulam Sewerage Treatment Plant at Kochi-Supply and Erection of Ring Main Unit (RMU) to new 5 MLD STP at Elamkulam - HT - Electrical Work-1 | Kochi Project Division |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Mar 2023 | STP functioning in full swing. | Kochi JNURM Projects AE-6 | |
07 Dec 2022 | STP functioning in full swing. | Kochi JNURM Projects AE-6 | |
17 Oct 2022 | Work in progress at receiving chamber - extension of one pipeline fixed. Welding of second pipeline on progress. | Kochi JNURM Projects AE-6 | |
12 Oct 2022 | Trial run in progress. Inspection from Electrical Inspectorate completed. Rectification measures instructed by Inspectorate is in progress, NoC from Corporation for submitting to Inspectorate and KSEB for getting HT connection awaiting. | Kochi WS Project Dn AEE-2 | |
13 Sep 2022 | Trial run in progress. KSEB connection application pending at DCE, KSEB Ernakulam office | Kochi WS Project Dn AEE-2 |
Date of start of Project | 17/12/2020 |
---|---|
Scheduled date of Completion of the Project | 31 Mar 2022 |
Expected date of Completion | 31/10/2022 |
AS Date | 01 Jan 2018 |
---|---|
TS Date | 08 Feb 2018 |
Project Officers | View |
---|