| Project | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi |
|---|---|
| Project Code | EKMAMRUT0118684P2 |
| Type | Package |
| Main Project | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi |
| Funding Agency | AMRUT |
| Category | AMRUT | Type of scheme | Water Supply |
| Description | AMRUT - Rejuvenation of Elamkulam Sewage Treatment Plant at Kochi |
| Status | On-going |
| District | Ernakulam |
| Executing Office | JnNURM Project WS Dn |
| TS Amount (Rs) | 137000000 |
| TS Number | ORDER No. TS - CE/CR/KWA/71/17-18 dated 08.02.2018 |
| Technical specification | New 5 STP was based on the treatment process Moving Bed Biofilm Bio Reactor (MBBR) method. This process includes primary, Secondary and tertiary level treatment. |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 17/12/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 24 Mar 2022 |
| Expected date of Completion | 24/03/2022 |
| TS Date | 08 Aug 2018 |
|---|---|
| Estimate Approval | 17 Feb 2018 |
| NIT Approval | 17 Feb 2018 |
| Tender Closing | 03 Dec 2018 |
| Technichal Pre-Qualification | 06 Jan 2019 |
| Price bid opening | 17 Jan 2019 |
| Workorder Date | 14 Jan 2020 |
|---|---|
| Agreement Date | 28 Dec 2020 |
| Kochi Drainage Sn AE |
| Date: 05/07/2021 |
Work in progress | 36% Completed
Equalization tank Pilecap concreting completed .
| Kochi Drainage Sn AE |
| Date: 02/07/2021 |
Work in progress | 36% Completed
Reinforcement work & shuttering work of Pile cap of Equalisation tank in progress.