- Home
- Jal Jeevan Mission 2021-2022- Supplying,...
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Project |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III |
Project Code |
PKDJJM022212214 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
57600000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
51300000 |
TS Number |
TS/2022-2023/2021/26622 |
Total Bill Submitted (Rs) |
26422062 |
Total Bill Paid (Rs) |
26422062 |
Population Benefitted |
27971 |
Capacity in MLD |
6.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
356nos |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III |
Pattambi PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work is progressing. |
Shornur PH Dn EE |
|
16 Aug 2023 |
9900m 90mm HDPE Pipe laid , geo-tagging 300 no, 160mm PVC pipe 3460m laid, 310 nos Billed , 80mm GI pipe 2900m laid , 150mm GI pipe 200m laid |
Shornur PH Dn EE |
|
06 Feb 2023 |
8700m 90mm HDPE Pipe laid , geo-tagging 220 no, 160mm PVC pipe 3300m laid, 165 nos house connection provide
|
Shornur PH Dn EE |
|
27 Dec 2022 |
Pipe laying 6000m HDPE , geo-tagging 220 no, 160mm PVC laying work progressing , 100 nos house connection provided.
|
Shornur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/07/2022 |
Scheduled date of Completion of the Project |
21 Jan 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
10 May 2022 |