Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work is progressing. Shornur PH Dn EE
16 Aug 2023 9900m 90mm HDPE Pipe laid , geo-tagging 300 no, 160mm PVC pipe 3460m laid, 310 nos Billed , 80mm GI pipe 2900m laid , 150mm GI pipe 200m laid Shornur PH Dn EE
06 Feb 2023 8700m 90mm HDPE Pipe laid , geo-tagging 220 no, 160mm PVC pipe 3300m laid, 165 nos house connection provide Shornur PH Dn EE
27 Dec 2022 Pipe laying 6000m HDPE , geo-tagging 220 no, 160mm PVC laying work progressing , 100 nos house connection provided. Shornur PH Dn EE