Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2024 | 9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work is progressing. | Shornur PH Dn EE | |
16 Aug 2023 | 9900m 90mm HDPE Pipe laid , geo-tagging 300 no, 160mm PVC pipe 3460m laid, 310 nos Billed , 80mm GI pipe 2900m laid , 150mm GI pipe 200m laid | Shornur PH Dn EE | |
06 Feb 2023 | 8700m 90mm HDPE Pipe laid , geo-tagging 220 no, 160mm PVC pipe 3300m laid, 165 nos house connection provide | Shornur PH Dn EE | |
27 Dec 2022 | Pipe laying 6000m HDPE , geo-tagging 220 no, 160mm PVC laying work progressing , 100 nos house connection provided. | Shornur PH Dn EE |