Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III

Project Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Project Code PKDJJM022212214P1
Type Package
Main Project Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 51300000
TS Number TS/2022-2023/2021/26622
Technical specification Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Contractor M/S HORIZIA CONSTRUCTION INDIA PRIVATE LIMIITED (Mob: 9447626777)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/09/2022
Scheduled date of Completion as per agreement 21 Jan 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 10 May 2022
Estimate Approval 10 May 2022
Tender Closing 17 Jun 2022
Price bid opening 20 Jun 2022

Approval Dates

Workorder Date 22 Jul 2022
NA 14 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 01/07/2024

Work in progress | 96% Completed

9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155.9m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work completed, final bill submitted.

Pattambi PH Sn AE
Date: 26/06/2024

Work in progress | 96% Completed

9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155.9m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work completed, final bill submitted .