Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
Project |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III |
Project Code |
PKDJJM022212214P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2021-2022- Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
|
Status |
On-going |
District |
Palakkad |
Executing Office |
Pattambi PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
51300000 |
TS Number |
TS/2022-2023/2021/26622 |
Technical specification |
Supplying, laying, testing, commissioning and Mace of distribution system, providing FHTCs (356nos), supply, erection, commissioning of raw water pump set and transformer, refurbishing the filter beds with dual media and road restoration works in Kulukkallur Grama Panchayath- Phase III
|
Contractor |
M/S HORIZIA CONSTRUCTION INDIA PRIVATE LIMIITED (Mob: 9447626777) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
14/09/2022 |
Scheduled date of Completion as per agreement |
21 Jan 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
TS Date |
10 May 2022 |
Estimate Approval |
10 May 2022 |
Tender Closing |
17 Jun 2022 |
Price bid opening |
20 Jun 2022 |
Approval Dates
Workorder Date |
22 Jul 2022 |
NA |
14 Sep 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Pattambi PH Sn AE |
Date: 01/07/2024 |
Work in progress | 96% Completed
9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155.9m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work completed, final bill submitted.
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work in progress | 96% Completed
9950m 90mm HDPE Pipe laid , 160mm PVC pipe 4155.9m laid, 356 nos FHTC provided , 80mm GI pipe 3176m laid , 150mm GI pipe 300m laid ,150HP motor pump set , transformer are supplied. work completed n filter bed & transformers work completed, final bill submitted
.