Kasaragod Development Package-2019-20-WSS to Government Medical college , Kasaragod
| Project |
Kasaragod Development Package-2019-20-WSS to Government Medical college , Kasaragod |
| Project Code |
KGDDEPO02204809 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
KDP |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Construction of clear water pump house, Supplying and laying clear water pumping main and pumpsets and construction of OHSR |
| Status |
On-going |
| District |
Kasaragod |
| Executing Office |
Kanhangad Project Division |
| AS Amount (Rs) |
80000000
|
| AS Number |
GO.(RT)No.65/2020/PE&A |
| TS Amount (Rs) |
64200000 |
| TS Number |
17191/2020-21 |
| Total Bill Submitted (Rs) |
44618633 |
| Total Bill Paid (Rs) |
41255306 |
| Population Benefitted |
10947 |
| Capacity in MLD |
1.00 |
| Actual Project Completion Date |
31 Dec 2024 |
| Coverage |
WSS to Medical college campus,Kasaragod
|
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Kasaragod Development Package-2019-20-WSS to Government Medical college , Kasaragod |
Project Division Kannur ( KGD) |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 25 Oct 2025 |
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval. |
Kanhangad Proj Dn AE - 2 |
|
| 22 Oct 2025 |
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval |
Kanhangad Proj Dn AE - 2 |
|
| 18 Oct 2025 |
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval |
Kanhangad Proj Dn AE - 2 |
|
| 13 Oct 2025 |
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. |
Kanhangad Proj Dn AE - 2 |
|
| 04 Oct 2025 |
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. |
Kanhangad Proj Dn AE - 2 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
03/12/2021 |
| Scheduled date of Completion of the Project |
14 Aug 2022 |
| Expected date of Completion |
31/03/2027 |
Processing Dates
| AS Date |
03 Feb 2020 |
| TS Date |
17 Feb 2021 |