| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Oct 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval. | Kanhangad Proj Dn AE - 2 | |
| 22 Oct 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval | Kanhangad Proj Dn AE - 2 | |
| 18 Oct 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed.RE is submitted for approval | Kanhangad Proj Dn AE - 2 | |
| 13 Oct 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 04 Oct 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 25 Sep 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 20 Sep 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 15 Sep 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 10 Sep 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 | |
| 30 Aug 2025 | Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. | Kanhangad Proj Dn AE - 2 |