| Project | Kasaragod Development Package-2019-20-WSS to Government Medical college , Kasaragod |
|---|---|
| Project Code | KGDDEPO02204809P2 |
| Type | Package |
| Main Project | Kasaragod Development Package-2019-20-WSS to Government Medical college , Kasaragod |
| Funding Agency | DEPO |
| Category | KDP |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Construction of pump house, pumping main, OHSR |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Project Division Kannur ( KGD) |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 64200000 |
| TS Number | TS/2020-21/2020/4675 |
| Technical specification | For water supply to the Kasargod medical coolege |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 03/12/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Aug 2022 |
| Expected date of Completion | 31/03/2027 |
| TS Date | 23 Jan 2021 |
|---|---|
| Estimate Approval | 23 Jan 2021 |
| NIT Approval | 12 Jul 2021 |
| Tender Closing | 26 Jul 2021 |
| Price bid opening | 29 Jul 2021 |
| Workorder Date | 15 Nov 2021 |
|---|---|
| NA | 01 Dec 2021 |
| Kanhangad Proj Dn AE - 2 |
| Date: 29/05/2026 |
Work in progress | 95% Completed
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. .
| Kanhangad Proj Dn AE - 2 |
| Date: 28/04/2026 |
Work in progress | 95% Completed
Work in progress. Concrete work for the 10 LL OHSR at Ukkinadukka completed. RE is submitted for approval.