Project | JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath |
---|---|
Project Code | PKDJJM052213171P1 |
Type | Package |
Main Project | JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 304600000 |
TS Number | WRD/KWA-CE(NR)/EST-TS/3982/2022 |
Technical specification | JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath |
Contractor | SALIL VARGHESE (Mob: 9447270099) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Sep 2022 | Pending | Pending | Land Related Risk | 0.52 hectare of forest land to be obtained | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/06/2023 |
---|---|
Scheduled date of Completion as per agreement | 09 May 2024 |
Expected date of Completion | 30/05/2024 |
TS Date | 21 Oct 2022 |
---|---|
Estimate Approval | 09 Feb 2023 |
NIT Approval | 21 Oct 2022 |
Tender Closing | 13 Mar 2023 |
Technichal Pre-Qualification | 25 Apr 2023 |
Price bid opening | 10 May 2023 |
Workorder Date | 26 Apr 2023 |
---|---|
NA | 09 May 2023 |
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 15% Completed
36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. .
Palakkad Proj AE 3 |
Date: 25/06/2024 |
Work in progress | 15% Completed
36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. .