JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath

Project JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Project Code PKDJJM052213171P1
Type Package
Main Project JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 304600000
TS Number WRD/KWA-CE(NR)/EST-TS/3982/2022
Technical specification JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Contractor SALIL VARGHESE (Mob: 9447270099)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Sep 2022 Pending Pending Land Related Risk 0.52 hectare of forest land to be obtained No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/06/2023
Scheduled date of Completion as per agreement 09 May 2024
Expected date of Completion 30/05/2024

Processing Dates

TS Date 21 Oct 2022
Estimate Approval 09 Feb 2023
NIT Approval 21 Oct 2022
Tender Closing 13 Mar 2023
Technichal Pre-Qualification 25 Apr 2023
Price bid opening 10 May 2023

Approval Dates

Workorder Date 26 Apr 2023
NA 09 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 15% Completed

36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. .

Palakkad Proj AE 3
Date: 25/06/2024

Work in progress | 15% Completed

36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. .