Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21- Pallikathodu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC

Project JJM 2020-21- Pallikathodu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC
Project Code KTMJJM08204330
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description 14 km New distribution from GLSR at Challoli, 4.2km Extension of existing distribution , Providing total 1200 FHTCs
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 241500000
AS Number GO(Rt)541/2020/WRD
TS Amount (Rs) 50300000
TS Number TS/2020-2021/2020/19733
Total Bill Submitted (Rs) 32218683
Total Bill Paid (Rs) 32218683
Population Benefitted 5500
Capacity in MLD 0.20
Actual Project Completion Date 31 Mar 2023
Coverage WARD 5,7
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2020-21- WSS to Pallikathode panchayath - supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 2 - Mathrumala Area Kottayam Project Dn
2 JJM 2020-21- WSS to Pallikathode panchayath - Supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 3- Challoli Area Kottayam Project Dn
3 PACKAGE (4A) Kottayam Project Dn
4 SUPPLYING AND LAYING DI/PVC/GIDISTRIBUTION NETWORK AND PROVIDING FHTCS (5th SLSSC) Supplying and laying 350 mm DI CWPM from WTP to OHSR at Mathrumala (Reach 2) Kottayam Project Dn
5 WSS TO PALLICKATHODU PANCHAYAT- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH) Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Jan 2023 Package 1-12km out of 14km laid.Pipelaying work progressing.400/1200 connections given.Package 2-33km out of 48km .513/725 connections given.Package 3-31km out of 55km .146/725 connections given. Kottayam AE 3
04 Jul 2022 Package 1-7km out of 14km laid.Pipelaying work progressing.190/1200 connections given.Package 2-22 km 90 HDPE pipe laying in progress.Heavy rains is interupts the pipe laying works.Package 3-13 km pipe laying completed and works is progressing.Heavy rain is interupts the pipe laying Kottayam AE 3
09 Nov 2021 4.5 km out of 14 km completed. PWD sanction obtained for a length of 6360m on 13/10/2021 and except 560 m (Joint inspection carried out on 11.10.2021) in Oravakkal – Koorali road. In other roads works started and in progress. 60/1200 connections given. Original date of completion expired on 30/04/2021 and the application from contractor for the extension submitted to higher office up to 31/01/2022 considering the ban on sabrimala season upto Jan 15 and the non availability PWD road cutting sanction the Oravakkal – Koorali Road . Kottayam AE 3
07 Nov 2021 Total 3073m PVC pipe and 427m DI pipe laid and 60/1200 FHTCs given Kottayam AE 3
01 Oct 2021 Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. Kottayam AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Jun 2021 Very poor progress. Add dated photographs. Add correspondence regarding PWD issues in the documents.ALL THE DOCUMENTS TO BE UPLOADED AE,AEE
10 Feb 2021 ADD PACKAGE 2 EE,AE

Duration & Sanction dates

Date of start of Project 28/12/2020
Scheduled date of Completion of the Project 30 Apr 2021
Expected date of Completion 31/05/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 25 Sep 2020

Other details

Project Officers View