Project | JJM 2020-21- Pallikathodu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC |
---|---|
Project Code | KTMJJM08204330 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | 14 km New distribution from GLSR at Challoli, 4.2km Extension of existing distribution , Providing total 1200 FHTCs |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 241500000 |
AS Number | GO(Rt)541/2020/WRD |
TS Amount (Rs) | 50300000 |
TS Number | TS/2020-2021/2020/19733 |
Total Bill Submitted (Rs) | 32218683 |
Total Bill Paid (Rs) | 32218683 |
Population Benefitted | 5500 |
Capacity in MLD | 0.20 |
Actual Project Completion Date | 31 Mar 2023 |
Coverage | WARD 5,7 |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | JJM 2020-21- WSS to Pallikathode panchayath - supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 2 - Mathrumala Area | Kottayam Project Dn | |
2 | JJM 2020-21- WSS to Pallikathode panchayath - Supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 3- Challoli Area | Kottayam Project Dn | |
3 | PACKAGE (4A) | Kottayam Project Dn | |
4 | SUPPLYING AND LAYING DI/PVC/GIDISTRIBUTION NETWORK AND PROVIDING FHTCS (5th SLSSC) Supplying and laying 350 mm DI CWPM from WTP to OHSR at Mathrumala (Reach 2) | Kottayam Project Dn | |
5 | WSS TO PALLICKATHODU PANCHAYAT- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH) | Kottayam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Jan 2023 | Package 1-12km out of 14km laid.Pipelaying work progressing.400/1200 connections given.Package 2-33km out of 48km .513/725 connections given.Package 3-31km out of 55km .146/725 connections given. | Kottayam AE 3 | |
04 Jul 2022 | Package 1-7km out of 14km laid.Pipelaying work progressing.190/1200 connections given.Package 2-22 km 90 HDPE pipe laying in progress.Heavy rains is interupts the pipe laying works.Package 3-13 km pipe laying completed and works is progressing.Heavy rain is interupts the pipe laying | Kottayam AE 3 | |
09 Nov 2021 | 4.5 km out of 14 km completed. PWD sanction obtained for a length of 6360m on 13/10/2021 and except 560 m (Joint inspection carried out on 11.10.2021) in Oravakkal – Koorali road. In other roads works started and in progress. 60/1200 connections given. Original date of completion expired on 30/04/2021 and the application from contractor for the extension submitted to higher office up to 31/01/2022 considering the ban on sabrimala season upto Jan 15 and the non availability PWD road cutting sanction the Oravakkal – Koorali Road . | Kottayam AE 3 | |
07 Nov 2021 | Total 3073m PVC pipe and 427m DI pipe laid and 60/1200 FHTCs given | Kottayam AE 3 | |
01 Oct 2021 | Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. | Kottayam AE 3 |
Review Date | Review Message | Review Attended By |
---|---|---|
18 Jun 2021 | Very poor progress. Add dated photographs. Add correspondence regarding PWD issues in the documents.ALL THE DOCUMENTS TO BE UPLOADED | AE,AEE |
10 Feb 2021 | ADD PACKAGE 2 | EE,AE |
Date of start of Project | 28/12/2020 |
---|---|
Scheduled date of Completion of the Project | 30 Apr 2021 |
Expected date of Completion | 31/05/2023 |
AS Date | 21 Aug 2020 |
---|---|
TS Date | 25 Sep 2020 |
Project Officers | View |
---|