WSS TO PALLICKATHODU PANCHAYAT- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH)

Project WSS TO PALLICKATHODU PANCHAYAT- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH)
Project Code KTMJJM08204330P1
Type Package
Main Project JJM 2020-21- Pallikathodu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH)
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 50300000
TS Number TS/2020-2021/2020/19733
Technical specification SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC S IN CWSS TO MANIMALA AND ADJOINING PANCHAYATHS PHASE –II ZONE 3.(PALLIKATHODE PANCHAYATH)
Contractor SHONY P JACOB (Mob: 9447677787)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 28/12/2020
Scheduled date of Completion as per agreement 30 Apr 2021
Expected date of Completion 31/10/2022

Processing Dates

TS Date 25 Sep 2020
Estimate Approval 25 Sep 2020
NIT Approval 25 Sep 2020
Tender Closing 30 Sep 2020
Technichal Pre-Qualification 09 Oct 2020
Price bid opening 16 Oct 2020

Approval Dates

NA 18 Feb 2020
Workorder Date 31 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 26/06/2024

Work in progress | 83% Completed

FHTC laying has reached saturation level Panchayath members are requested to identify consumers with in ward 5,6,7,8 for closure of work .

Kottayam Proj Dn AE4
Date: 25/06/2024

Work in progress | 83% Completed

FHTC laying has reached saturation level Panchayath members are requested to identify consumers with in ward 5,6,7,8 for closure of work .