Project | JJM 2020-21- WSS to Pallikathode panchayath - Supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 3- Challoli Area |
---|---|
Project Code | KTMJJM08204330P3 |
Type | Package |
Main Project | JJM 2020-21- Pallikathodu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 3 -Challoli Area |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 88200000 |
TS Number | TS/2021-2022/2021/42097 |
Technical specification | Supplying and laying DI/PVC /GI distribution network and providing FHTCs in Manimala Phase II Zone III- Package 3 - Challoli Area |
Contractor | TOMICHEN K U (Mob: 9447980965) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 27/01/2022 |
---|---|
Scheduled date of Completion as per agreement | 26 Jul 2022 |
Expected date of Completion | 31/03/2023 |
TS Date | 23 Dec 2021 |
---|---|
Estimate Approval | 23 Dec 2021 |
NIT Approval | 28 Dec 2021 |
Tender Closing | 07 Jan 2022 |
Price bid opening | 11 Jan 2022 |
Workorder Date | 27 Jan 2022 |
---|---|
NA | 08 Feb 2022 |
Kottayam Proj Dn AE4 |
Date: 26/06/2024 |
Work in progress | 90% Completed
PWD permission not obtained. 400 mm DI K9 pipes not supplied by the contractor. .
Kottayam Proj Dn AE4 |
Date: 25/06/2024 |
Work in progress | 90% Completed
PWD permission not obtained. 400 mm DI K9 pipes not supplied by the contractor. .