| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - POTTAMMEL ZONE-EXTENSION AND REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING FHTC IN PWD ROADS PATTERI - MAVOOR ROAD - PUTHIYARA-Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P36 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - POTTAMMEL ZONE-EXTENSION AND REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING FHTC IN PWD ROADS PATTERI - MAVOOR ROAD - PUTHIYARA-Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 1 Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 9830000 |
| TS Number | 6967/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/11/2024 |
| TS Date | 23 Jun 2023 |
|---|---|
| Estimate Approval | 22 Jun 2023 |
| Tender Closing | 18 Aug 2023 |
| Workorder Date | 26 Sep 2023 |
|---|---|
| NA | 27 Oct 2023 |
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 73% Completed
1350 m laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 70% Completed
1000 m laying completed.