| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 73% Completed
1350 m laying completed
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 70% Completed
1000 m laying completed
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 18/03/2025 |
Work in progress | 60% Completed
work started
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 12/02/2025 |
Work in progress | 31% Completed
PBG and Chalan submitted.But not approved by PWD.Thus work not started.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 24/01/2025 |
Work in progress | 31% Completed
PBG and Chalan submitted.But not approved by PWD.Thus work not started.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 16/01/2025 |
Work in progress | 30% Completed
PBG and Chalan submitted.But not approved by PWD.Thus work not started.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 07/12/2024 |
Work in progress | 25% Completed
PBG and Chalan submitted.But not approved by PWD.Thus work not started.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 19/11/2024 |
Work in progress | 20% Completed
PBG and Chalan submitted.But not approved by PWD.Thus work not started.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 06/11/2024 |
Work in progress | 20% Completed
PWD road cutting permission pending and work not started
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 26/10/2024 |
Work in progress | 20% Completed
PWD road cutting permission pending and work not started
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work in progress | 20% Completed
PWD road cutting permission pending and work not started
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 20% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work has started | 0% Completed
Work Not Started
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work has started | 0% Completed
Work Not Started
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work has started | 0% Completed
Work Not Started
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work has started | 0% Completed
Work Not Started
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work has started | 0% Completed
Join Inspection completed
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work has started | 0% Completed
Waiting for road cutting permission
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work has started | 0% Completed
Agreement Executed