Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thaliparamba WS Section
Date: 28/09/2026

Work in progress | 98% Completed

Work completed. RE on forwarded for approval

Thaliparamba WS Section
Date: 02/07/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 25/06/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 09/06/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 12/05/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 24/04/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 07/04/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 27/03/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 13/03/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 04/03/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 21/02/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 16/02/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 06/02/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 28/01/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 23/01/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 17/01/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 12/01/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Dn EE
Date: 09/01/2026

Work in progress | 95% Completed

95% completed.

Thaliparamba WS Section
Date: 07/01/2026

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 31/12/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 22/12/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 15/12/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 01/12/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 22/11/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 13/11/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 04/11/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 28/10/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 22/10/2025

Work in progress | 95% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed

Thaliparamba WS Section
Date: 15/10/2025

Work in progress | 92% Completed

Interconnection work with 900mm DI pipe completed. Pipe laying balance work started

Thaliparamba WS Section
Date: 03/10/2025

Work in progress | 92% Completed

Interconnection work with 900mm DI pipe completed. Finishing works pending

Thaliparamba WS Sub Dn
Date: 27/06/2025

Work in progress | 90% Completed

Interconnection work with 900mm DI pipe pending. Finishing works pending

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 85% Completed

Road restoration work completed

Thaliparamba WS Section
Date: 30/04/2025

Work in progress | 65% Completed

DI completed. Road restoration work started.

Thaliparamba WS Section
Date: 01/02/2025

Work in progress | 46% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 27/11/2024

Work in progress | 45% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 11/11/2024

Work in progress | 45% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 05/11/2024

Work in progress | 40% Completed

OHSR's concrete work & plastering completed

Thaliparamba WS Section
Date: 30/10/2024

Work in progress | 40% Completed

OHSR's concrete work & plastering completed

Thaliparamba WS Section
Date: 23/10/2024

Work in progress | 35% Completed

OHSR concrete work completed, plastering under progress

Thaliparamba WS Section
Date: 09/10/2024

Work in progress | 30% Completed

OHSR covering slab concrete completed

Thaliparamba WS Section
Date: 01/10/2024

Work in progress | 30% Completed

OHSR covering slab concrete completed

Thaliparamba WS Section
Date: 25/09/2024

Work in progress | 20% Completed

Tank work up to OHSR side wall concrete completed

Thaliparamba WS Section
Date: 18/09/2024

Work in progress | 10% Completed

Tank work up to deck slab completed

Thaliparamba WS Section
Date: 02/09/2024

Work in progress | 3% Completed

Tank work upto first bracing completed

Thaliparamba WS Section
Date: 26/06/2024

Work has started | 0% Completed

Work order issued on 16.03.2024

Thaliparamba WS Section
Date: 04/04/2024

Work has started | 0% Completed

Work order issued on 16.03.2024

Thaliparamba WS Dn EE
Date: 25/03/2024

Work has started | 0% Completed

Work Order issued on 16.03.2024.