| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 98% Completed
Work completed. RE on forwarded for approval
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 25/06/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 09/06/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 12/05/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 24/04/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 07/04/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 27/03/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 13/03/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 04/03/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 21/02/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 16/02/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 06/02/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 28/01/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 23/01/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 17/01/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 12/01/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Dn EE |
| Date: 09/01/2026 |
Work in progress | 95% Completed
95% completed.
| Thaliparamba WS Section |
| Date: 07/01/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 31/12/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 22/12/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 15/12/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 01/12/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 22/11/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 13/11/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 04/11/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 28/10/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 22/10/2025 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed
| Thaliparamba WS Section |
| Date: 15/10/2025 |
Work in progress | 92% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work started
| Thaliparamba WS Section |
| Date: 03/10/2025 |
Work in progress | 92% Completed
Interconnection work with 900mm DI pipe completed. Finishing works pending
| Thaliparamba WS Sub Dn |
| Date: 27/06/2025 |
Work in progress | 90% Completed
Interconnection work with 900mm DI pipe pending. Finishing works pending
| Thaliparamba WS Section |
| Date: 19/06/2025 |
Work in progress | 85% Completed
Road restoration work completed
| Thaliparamba WS Section |
| Date: 30/04/2025 |
Work in progress | 65% Completed
DI completed. Road restoration work started.
| Thaliparamba WS Section |
| Date: 01/02/2025 |
Work in progress | 46% Completed
OHSR's concrete work & plastering completed, DI Laying started
| Thaliparamba WS Section |
| Date: 27/11/2024 |
Work in progress | 45% Completed
OHSR's concrete work & plastering completed, DI Laying started
| Thaliparamba WS Section |
| Date: 11/11/2024 |
Work in progress | 45% Completed
OHSR's concrete work & plastering completed, DI Laying started
| Thaliparamba WS Section |
| Date: 05/11/2024 |
Work in progress | 40% Completed
OHSR's concrete work & plastering completed
| Thaliparamba WS Section |
| Date: 30/10/2024 |
Work in progress | 40% Completed
OHSR's concrete work & plastering completed
| Thaliparamba WS Section |
| Date: 23/10/2024 |
Work in progress | 35% Completed
OHSR concrete work completed, plastering under progress
| Thaliparamba WS Section |
| Date: 09/10/2024 |
Work in progress | 30% Completed
OHSR covering slab concrete completed
| Thaliparamba WS Section |
| Date: 01/10/2024 |
Work in progress | 30% Completed
OHSR covering slab concrete completed
| Thaliparamba WS Section |
| Date: 25/09/2024 |
Work in progress | 20% Completed
Tank work up to OHSR side wall concrete completed
| Thaliparamba WS Section |
| Date: 18/09/2024 |
Work in progress | 10% Completed
Tank work up to deck slab completed
| Thaliparamba WS Section |
| Date: 02/09/2024 |
Work in progress | 3% Completed
Tank work upto first bracing completed
| Thaliparamba WS Section |
| Date: 26/06/2024 |
Work has started | 0% Completed
Work order issued on 16.03.2024
| Thaliparamba WS Section |
| Date: 04/04/2024 |
Work has started | 0% Completed
Work order issued on 16.03.2024
| Thaliparamba WS Dn EE |
| Date: 25/03/2024 |
Work has started | 0% Completed
Work Order issued on 16.03.2024.