Project | Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath |
---|---|
Project Code | KLMJJM082014881P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath.-Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath |
Status | On-going |
District | Kollam |
Executing Office | Chathannoor PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 3000000 |
TS Number | WRD/KWA-CE(SR)/EST_TS/17658/2023_26_1_1 |
Technical specification | Laying of balance distribution net work in Poothakkulam GP 1. Supply of PVC Pipe, 6kg/cm2, 160mm Dia.- 396m 2. - Supply of PVC Pipe, 6kg/cm2, 90mm Dia- 1500m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 11/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 10 Dec 2023 |
Expected date of Completion | 10/12/2023 |
TS Date | 15 Jul 2023 |
---|---|
Estimate Approval | 15 Jul 2023 |
NIT Approval | 15 Jul 2023 |
Tender Closing | 25 Jul 2023 |
Technichal Pre-Qualification | 27 Jul 2023 |
Price bid opening | 27 Jul 2023 |
Workorder Date | 01 Aug 2023 |
---|---|
NA | 11 Aug 2023 |
Chathannur PH Sn AE |
Date: 02/07/2024 |
Work in progress | 53% Completed
90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock.
Chathannur PH Sn AE |
Date: 01/07/2024 |
Work in progress | 53% Completed
90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock.