Time extension

30/09/2022 | File: time extension.pdf | Download

The works could not be progressed as scheduled since the consumer houses are far away from the existing KWA service lines and there is shortage of water supply at many areas . Hence identifying the feasible consumers is not easy. The resurfacing work of the road was completed and the Roads is under DLP. Hence the road cutting sanction cannot be be granted. Hence the extension for the work may be granted without imposing fine.