| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Feb 2026 | Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started | Thaliparamba WS Section | |
| 16 Feb 2026 | Pipe laying for 3km completed and existing connection restored for 3km | Thaliparamba WS Section | |
| 06 Feb 2026 | Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started. | Thaliparamba WS Section | |
| 28 Jan 2026 | Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started. | Thaliparamba WS Section | |
| 23 Jan 2026 | Tank work upto second brace beam completed. PVC pipe laid for 2km. DI laying work started. | Thaliparamba WS Section | |
| 17 Jan 2026 | Tank work upto second brace beam completed. PVC pipe laid for 2km | Thaliparamba WS Section | |
| 12 Jan 2026 | Second brace beam completed | Thaliparamba WS Section | |
| 07 Jan 2026 | Second brace beam completed | Thaliparamba WS Section | |
| 31 Dec 2025 | Second brace beam completed | Thaliparamba WS Section | |
| 22 Dec 2025 | First brace beam work completed | Thaliparamba WS Section |