Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2026 Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started Thaliparamba WS Section
16 Feb 2026 Pipe laying for 3km completed and existing connection restored for 3km Thaliparamba WS Section
06 Feb 2026 Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started. Thaliparamba WS Section
28 Jan 2026 Tank work up to deck beam completed. PVC pipe laid for 2km. DI laying work started. Thaliparamba WS Section
23 Jan 2026 Tank work upto second brace beam completed. PVC pipe laid for 2km. DI laying work started. Thaliparamba WS Section
17 Jan 2026 Tank work upto second brace beam completed. PVC pipe laid for 2km Thaliparamba WS Section
12 Jan 2026 Second brace beam completed Thaliparamba WS Section
07 Jan 2026 Second brace beam completed Thaliparamba WS Section
31 Dec 2025 Second brace beam completed Thaliparamba WS Section
22 Dec 2025 First brace beam work completed Thaliparamba WS Section