Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Jun 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
13 Jun 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
06 Jun 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
08 May 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
22 Apr 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
17 Apr 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
06 Apr 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed. |
Alappuzha Project Dn PM |
|
20 Mar 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths,90 mm PVC laid out of 11000 meter PVC pipe to be laid, 10560 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 1332 meter laying has been completed.
|
Alappuzha Project Dn PM |
|
21 Feb 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 11989 FHTCs done, Out of 163 km of laying, around 161.7 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths, 90 mm PVC laid out of 11000 meter PVC pipe to be laid, 7686 meter laying has been completed, 90 mm PVC laid out of 11000 meter PVC pipe to be laid, 8580 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 0 meter laying has been completed. |
Alappuzha Project Dn PM |
|
12 Feb 2024 |
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 11989 FHTCs done, Out of 163 km of laying, around 161.7 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths, 90 mm PVC laid out of 11000 meter PVC pipe to be laid, 7686 meter laying has been completed, 90 mm PVC laid out of 11000 meter PVC pipe to be laid, 8580 meter laying has been completed, 110 mm PVC laid out of 2000 meter PVC pipe to be laid, 0 meter laying has been completed. |
Alappuzha Project Dn PM |
|