Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Aug 2022 | Laying of Pipes and providing FHTCs in progress | Alappuzha Project Dn PM | |
08 Aug 2022 | Laying of Pipes and providing FHTCs in progress | Alappuzha Project Dn PM | |
15 Jun 2022 | Laying of Pipes and providing FHTCs in progress. | Alappuzha Project Dn PM | |
03 Feb 2022 | Construction of 6.0 LL OHSR, Renovation of WTP Pattoor, Pipe laying and FHTC is under progress | Alappuzha Project Dn PM | |
05 Jan 2022 | Renovation of 10MLD WTP, construction of 6LL OHSR, Laying of Pipelines and providing FHTC in progress | Alappuzha Project Dn PM | |
05 Jan 2022 | Laying of Pipeline and providing FHTC in progress | Alappuzha Project Dn PM | |
04 Jan 2022 | CC 6 th and part bill submitted. Pipe laying 5463 meter completed and FHTC connection (2768 nos) has been completed. | Alappuzha Project Dn PM | |
24 Oct 2021 | Survey work completed and letter given to Govt polytechnic college Adoor for material testing and mix design. Site clearence work for construction of OHSR progressing. Pipe testing QAP submitted and intimation letter given to M/s CIPET for Pipe testing | Alappuzha Project Dn DPM2 | |
09 Sep 2021 | Survey work completed and letter given to Govt polytechnic college Adoor for material testing and mix design. Site clearence work for construction of OHSR progressing. Pipe testing QAP submitted and intimation letter given to M/s CIPET for Pipe testing | Alappuzha Project Dn PM | |
08 Sep 2021 | Survey work completed and letter given to Govt polytechnic college Adoor for material testing and mix design. Site clearence work for construction of OHSR progressing. Pipe testing QAP submitted and intimation letter given to M/s CIPET for Pipe testing | Alappuzha Proj Dn AE 2 |