Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Sep 2023 Plastering work completed- OHSR Pattoor- Nooranadu, Out of 23000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 161.25 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths. Alappuzha Project Dn PM
14 Aug 2023 Plastering work completed- OHSR Pattoor- Nooranadu, Out of 25000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 160 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths Alappuzha Project Dn AE 3
29 Jul 2023 Plastering work completed- OHSR Pattoor- Nooranadu, Out of 25000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 160 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths Alappuzha Project Dn AE 3
27 Jul 2023 Plastering work in progress- OHSR Pattoor, Nooranadu, House connection thamarakulam 2 nos Alappuzha Project Dn PM
19 Jul 2023 OHSR Pattoor Nooranadu-Plastering of innerside of OHSR in progress, Waterproofing of clariflocculator in progress ,Maintenance work of clariflocculator in progress Applying tile on the surface of aereater,Connections Thamarakulam -4 Alappuzha Project Dn PM
03 Jul 2023 Valve chamber-Concrete of chamber and cover slab completed at Post office jn, Chunakkara Quantity -2.1m3,Concrete completed at Edappon , Nooranadu Quantity -1.8m3,Connection provided Palamel -4,Thamarakulam -3 Alappuzha Project Dn PM
19 Jun 2023 Valve chamber-Concrete of cover slab completed at Kottamukk jn Chunakkara Quantity -0.3m3,Concrete of valve chamber completed a)Kottamukku jn, Chunakkara b)pachakkadu, Thamarakulam Quantity -3.6m3,Connection provided Thamarakulam -3 Nooranadu -2,Restoration Concrete of road of Chunakkara panchayat in progress Alappuzha Project Dn PM
16 Jun 2023 Valve chamber-Reinforcement of valve chamber completed Near Bund road, Chunakkara Concrete of valve chamber completed At Pachakaadu, Thamarakulam Quantity -1.8m3,PCC completed at Pachakadu, Thamarakulam Quantity -0.3m3 Excavation completed , Kottamukk jn,Chunakkara Cover slab Concrete of cover slab completed at Chunakkara Quantity -0.34m Connection provided Thamarakulam -2 Palamel -2 Alappuzha Project Dn PM
08 Jun 2023 Valve chamber-Concrete of Cover slab completed at PWD road side Kudasanadu, Palamel Total quantity -0.22m3,byroad of PWD road Kudasanadu,Palamel Total quantity -0.338m 3, Chunakkara bund road Total quantity -0.338m3,Concrete of valve chamber completed at bund road,Chunakkara Total quantity -1.8m3,Excavation to construct valve chamber started at,Athikattukulanghara,Palamel,Near bund road, Chunakkara , Laying details ,Pipe-160mmPVC, No of pipes laid -52 ,Road-Charumoodu-Kottamukku, Chunakkara, House connection ,Nooranadu -2 at Pulimel Alappuzha Project Dn PM
01 Jun 2023 1.Pattoor OHSR-Waterproofing of OHSR in progress, Nooranadu,2.Valve chamber- Excavation of 7th and 8th valve chamber in progress at bund road, Chunakkara and pulimel, Nooranadu, Concrete of cover slab completed at Korattu jn, Thamarakulam Total quantity -0.34m3, House connections-Thamarakulam -4 Alappuzha Project Dn PM