Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Sep 2023 |
Plastering work completed- OHSR Pattoor- Nooranadu, Out of 23000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 161.25 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths.
|
Alappuzha Project Dn PM |
|
14 Aug 2023 |
Plastering work completed- OHSR Pattoor- Nooranadu, Out of 25000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 160 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths
|
Alappuzha Project Dn AE 3 |
|
29 Jul 2023 |
Plastering work completed- OHSR Pattoor- Nooranadu, Out of 25000 FHTCs, around 11800 FHTCs done, Out of 163 km of laying, around 160 km laying done in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths
|
Alappuzha Project Dn AE 3 |
|
27 Jul 2023 |
Plastering work in progress- OHSR Pattoor, Nooranadu, House connection thamarakulam 2 nos
|
Alappuzha Project Dn PM |
|
19 Jul 2023 |
OHSR Pattoor Nooranadu-Plastering of innerside of OHSR in progress, Waterproofing of clariflocculator in progress ,Maintenance work of clariflocculator in progress Applying tile on the surface of aereater,Connections Thamarakulam -4
|
Alappuzha Project Dn PM |
|
03 Jul 2023 |
Valve chamber-Concrete of chamber and cover slab completed at Post office jn, Chunakkara Quantity -2.1m3,Concrete completed at Edappon , Nooranadu Quantity -1.8m3,Connection provided Palamel -4,Thamarakulam -3
|
Alappuzha Project Dn PM |
|
19 Jun 2023 |
Valve chamber-Concrete of cover slab completed at Kottamukk jn Chunakkara Quantity -0.3m3,Concrete of valve chamber completed a)Kottamukku jn, Chunakkara b)pachakkadu, Thamarakulam Quantity -3.6m3,Connection provided Thamarakulam -3 Nooranadu -2,Restoration Concrete of road of Chunakkara panchayat in progress
|
Alappuzha Project Dn PM |
|
16 Jun 2023 |
Valve chamber-Reinforcement of valve chamber completed Near Bund road, Chunakkara Concrete of valve chamber completed At Pachakaadu, Thamarakulam Quantity -1.8m3,PCC completed at Pachakadu, Thamarakulam Quantity -0.3m3 Excavation completed , Kottamukk jn,Chunakkara Cover slab Concrete of cover slab completed at Chunakkara Quantity -0.34m Connection provided Thamarakulam -2 Palamel -2
|
Alappuzha Project Dn PM |
|
08 Jun 2023 |
Valve chamber-Concrete of Cover slab completed at PWD road side Kudasanadu, Palamel Total quantity -0.22m3,byroad of PWD road Kudasanadu,Palamel Total quantity -0.338m 3, Chunakkara bund road Total quantity -0.338m3,Concrete of valve chamber completed at bund road,Chunakkara Total quantity -1.8m3,Excavation to construct valve chamber started at,Athikattukulanghara,Palamel,Near bund road, Chunakkara , Laying details ,Pipe-160mmPVC, No of pipes laid -52 ,Road-Charumoodu-Kottamukku, Chunakkara, House connection ,Nooranadu -2 at Pulimel
|
Alappuzha Project Dn PM |
|
01 Jun 2023 |
1.Pattoor OHSR-Waterproofing of OHSR in progress, Nooranadu,2.Valve chamber- Excavation of 7th and 8th valve chamber in progress at bund road, Chunakkara and pulimel, Nooranadu, Concrete of cover slab completed at Korattu jn, Thamarakulam Total quantity -0.34m3, House connections-Thamarakulam -4
|
Alappuzha Project Dn PM |
|