| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Nov 2020 | Construction of well completed , Laying of Clear water Pumping Main to Vadakkevila OHSR 87 % Completed, Dedicated power line extension to WTP and intake well amount deposited to KSEB, Work 95% completed.Laying clear water pumping main to Vasoorichira OHSR Selection notice issued.Construction of weir across Kallada river executing through irrigation wing. | Kollam Project HD | |
| 17 Nov 2020 | Construction of well completed , Laying of Clear water Pumping Main to Vadakkevila OHSR 85 % Completed, Dedicated power line extension to WTP and intake wll amount deposited to KSEB, Work 95% completed.Laying clear water pumping main to Vasoorichira OHSR Selection notice issued.Construction of weir across Kallada river executing through irrigation wing. Over all 35% of work completed. | Kollam Project HD |