| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Jul 2022 | Packages I, II and IV 100% work completed. PackageIII- Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16- Selection notice was issued to the lowest tenderer at 10% above Estimate rate. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions.Taken up at Government level by MD on 24/05/2022. Package V - Design, Construction, Commissioning and maintaining of 100MLD WTP (1) Cascade Aerator– Structural works upto aerator dome slab completed.(2)Raw water channel- Pilecap(24 nos) at raw water channel completed.Shuttering work for plinth beam in progress(3) Clariflocculators(3.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl completed . Casting of central shaft up to third lift completed . Inner base slab works of flocculator completed. Piling works completed. Outer base slab completed. Sludge pipe laid.Haunch completed. shuttering of outer wall first lift in progress. (3.b) CFL 2 - flocculator base slab Completed.Piling works completed. Outer base slab completed. Baffle wall completed .Sludge pipe laid.Haunch completed. Outer RCC wall 1st &2nd lift completed. Concreting ofcentral shaft second lift. 7.75m lvl channel slab shuttering and rebar work in progress (3.c) CFL 3 - Piling works completed. flocculator base slab completed. RCC for outer base slab completed. Sludge pipe laid. Baffle wall completed . Haunch completed. Outer wall(first ,second lift) completed.(4) Filter House- All structural works at +12.3m lvl slab completed. +13.8m lvl bottom slab of wash water tank completed. Plastering work in progress. Starter concrete for wash water tank completed. Side wall of wash water tank(first lift) completed. Brick work for outer wall in pump house in progress. Cleaning inside pump house in progress. (5) Chemical House -Structural works completed. Block work completed. Plastering work completed.(6) Admin Building-Foundation works completed. Plinth beam works completed. Grade slab completed. Casting of stair first flight completed. Ground floor roof slab completed.Rebar for columns(1st lift) above ground floor slab in progress.(7) Chlorine building- Excavation work for footing completed. PCC for footing completed. RCC footing(18Nos) completed. Casting of pedestal columns completed. (8) Back wash Recovery tank- PCC for raft foundation completed. Raft foundation completed. Starter concrete for outer wall completed. Outer wall first lift(700mm width) completed. Dewatering in progress. | Kollam Project HD | |
| 13 Jul 2022 | Packages I, II and IV 100% work completed. PackageIII- Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16- Selection notice was issued to the lowest tenderer at 10% above Estimate rate. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions.Taken up at Government level by MD on 24/05/2022. Package V - Design, Construction, Commissioning and maintaining of 100MLD WTP (1) Cascade Aerator– Structural works upto aerator dome slab completed.(2)Raw water channel- Pilecap(24 nos) at raw water channel completed.Shuttering work for plinth beam in progress(3) Clariflocculators(3.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl completed . Casting of central shaft up to third lift completed . Inner base slab works of flocculator completed. Piling works completed. Outer base slab completed. Sludge pipe laid.Haunch completed. shuttering of outer wall first lift in progress. (3.b) CFL 2 - flocculator base slab Completed.Piling works completed. Outer base slab completed. Baffle wall completed .Sludge pipe laid.Haunch completed. Outer RCC wall 1st &2nd lift completed. Concreting ofcentral shaft second lift. 7.75m lvl channel slab shuttering and rebar work in progress (3.c) CFL 3 - Piling works completed. flocculator base slab completed. RCC for outer base slab completed. Sludge pipe laid. Baffle wall completed . Haunch completed. Outer wall(first ,second lift) completed.(4) Filter House- All structural works at +12.3m lvl slab completed. +13.8m lvl bottom slab of wash water tank completed. Plastering work in progress. Starter concrete for wash water tank completed. Side wall of wash water tank(first lift) completed. Brick work for outer wall in pump house in progress. Cleaning inside pump house in progress. (5) Chemical House -Structural works completed. Block work completed. Plastering work completed.(6) Admin Building-Foundation works completed. Plinth beam works completed. Grade slab completed. Casting of stair first flight completed. Ground floor roof slab completed.Rebar for columns(1st lift) above ground floor slab in progress.(7) Chlorine building- Excavation work for footing completed. PCC for footing completed. RCC footing(18Nos) completed. Casting of pedestal columns completed. (8) Back wash Recovery tank- PCC for raft foundation completed. Raft foundation completed. Starter concrete for outer wall completed. Outer wall first lift(700mm width) completed. Dewatering in progress. | Kollam Project HD | |
| 03 Jul 2022 | Package I & II 100% work completed. PackageIII- Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16- Selection notice was issued to the lowest tenderer at 10% above Estimate rate. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions.Taken up at Government level by MD on 24/05/2022. Package IV- This work executed through KSEB. Out of 4.5 km's of power line extension at Njankadavu 4.5 km's of work was completed by laying under ground cables. Now 100 % of ABC (Areal Bunched Cable) work completed by KSEB. Package V - Design, Construction, Commissioning and maintaining of 100MLD WTP - (1) Cascade Aerator– Structural works upto aerator dome slab completed. Pilecap(24 nos) at raw water channel completed.(2) Clariflocculators(2.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl completed . Casting of central shaft up to third lift completed . Inner base slab works of flocculator completed. Piling works completed. Outer base slab completed. Sludge pipe laid.Haunch completed. (2.b) CFL 2 - flocculator base slab Completed.Piling works completed. Outer base slab completed. Baffle wall completed .Sludge pipe laid.Haunch completed. Outer RCC wall (first lift) completed.outer wall 2nd lift shuttering works in progress. (2.c) CFL 3 - Piling works completed. flocculator base slab completed. RCC for outer base slab completed. Sludge pipe laid. Baffle wall completed . Haunch completed. Outer wall(first lift) completed. (3) Filter House- All structural works at +12.3m lvl slab completed. +13.8m lvl bottom slab of wash water tank completed. Plastering work in progress. Starter concrete for wash water tank completed. Side wall of wash water tank(first lift) completed. Brick work for outer wall in pump house in progress. Cleaning inside pump house in progress.(4) Chemical House -Structural works completed. Block work completed. Plastering work completed.(5) Admin Building-Foundation works completed. Plinth beam works completed. Grade slab completed. Casting of stair first flight completed. Ground floor roof slab completed .(6) Chlorine building- Excavation work for footing completed. PCC for footing completed. RCC footing(18Nos) completed. Casting of pedestal columns completed. Casting of ground floor roof slab completed.PCC preparation for neutralization pit in progress. (7) Back wash Recovery tank- PCC for raft foundation completed. Raft foundation completed. Starter concrete for outer wall completed. Outer wall (700mm width) completed. | Kollam Project HD | |
| 01 Jun 2022 | Package 1-Construction of 12m dia intake well at Njankadavu - Work completed on 15/02/2020 Package II - Supplying laying commissioning and maintaining 500mm DI K9 - Work completed. PackageIII- Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16- Selection notice was issued to the lowest tenderer at 10% above Estimate rate. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions.Taken up at Government level by MD on 24/05/2022. Package IV- This work executed through KSEB. Out of 4.5 km's of power line extension at Njankadavu 4.5 km's of work was completed by laying under ground cables. Now 100 % of ABC (Areal Bunched Cable) work completed by KSEB. Package V - Design, Construction, Commissioning and maintaining of 100MLD WTP - 1) Cascade Aerator– Structural works upto aerator dome slab completed.(2) Clariflocculators(2.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl completed . Casting of central shaft up to third lift completed . Inner base slab works of flocculator completed. Piling works completed. Outer base slab completed. Sludge pipe laid. (2.b) CFL 2 - flocculator base slab Completed.Piling works completed. Outer base slab completed. Baffle wall completed .Sludge pipe laid. Haunch 80% completed. (2.c) CFL 3 - Piling works completed. flocculator base slab completed. RCC for outer base slab completed. Sludge pipe laid. Baffle wall completed . (3) Filter House- All structural works at +12.3m lvl slab completed. +13.8m lvl bottom slab of wash water tank completed. Plastering work in progress. Starter concrete for wash water tank completed. (4) Chemical House -Structural works completed. Block work completed.Plastering work completed.(5) Admin Building-Foundation works completed. Plinth beam works completed. Grade slab completed. Casting of stair first flight completed. Ground floor roof slab rebar work in progress.(6) Chlorine building- Exacavation work for footing completed. PCC for footing completed. RCC footing(18Nos) completed. Casting of pedestal columns completed. (7) Back wash Recovery tank- PCC for raft foundation completed. | Kollam Project HD | |
| 28 May 2022 | 1)Construction of well completed . (2.) Clear Water Pumping main from WTP to 20LL OHSR at TP using 350mm DI SAAP YEAR 2017-18 - this work arranged as a sub work of WTP. (3.) Power line extension work executed through KSEB completed (4.) Construction of weir across Kallada River - The work retendered (Third) with due date on 26/2/22.Two bids recieved. Lowest quoted is 29.80% above tendered PAC. Selection notice was issued to Sri.Sasidharan, Metaguard Engineers and Contractors J/V with Binu Mathew at 10% above tendered PAC.But contractor is not willing to execute agreement. Hence recommended for government consideration on 24/5/2022 by M.D (5.) Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed. (6.) 100 MLD - WTP - work in progress. 76% of work completed. (1) Cascade Aerator—columns & beams up to cascade slab completed. (2) Clariflocculators, CFL 1 – Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works of clarifloculator completed..(2.b) CFL 2 - Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works of clarifloculator completed (2.c) CFL 3 - Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works of clarifloculator completed. (3) Filter House- completed , wash water tank completed up to base slab. Casting for columns above +12.3m lvl in progress. (4) Chemical House -Structural works completed. Block work and plastering completed.(5) Admin Building-coloums up to first floor completed. Over all 66 % of work completed. | Kollam Project HD | |
| 26 May 2022 | 1)Construction of well completed . (2.) Clear Water Pumping main from WTP to 20LL OHSR at TP using 350mm DI SAAP YEAR 2017-18 - this work arranged as a sub work of WTP. (3.) Power line extension work executed through KSEB completed (4.) Construction of weir across Kallada River - The work retendered (Third) with due date on 26/2/22.Two bids recieved,PQ will be send to CEs office on 03-03-2022 STC. Is scheduled on 11/03/2022.(5.) Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed. (6.) 100 MLD - WTP - work in progress. 66% of work completed. (1) Cascade Aerator—columns & beams up to cascade slab completed. (2) Clariflocculators, CFL 1 – Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works of clarifloculator completed..(2.b) CFL 2 - Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works ofclarifloculator (2.c) CFL 3 - Baffle walls of floculator completed. central shaft second lift completed. Inner and outer base slab works of clarifloculator completed. (3) Filter House- completed , wash water tank completed up to base slab.. Casting for columns above +12.3m lvl in progress. (4) Chemical House -Structural works completed Block work completed.(5) Admin Building-coloums up to first floor completed.. Over all 66 % of work completed. | Kollam Project HD | |
| 03 Apr 2022 | Work order issued for the work of construction of weir across Kallada River on 30.03.2022 | Kollam Project Dn EE | |
| 02 Apr 2022 | I.)Construction of well completed . (2.) Clear Water Pumping main from WTP to 20LL OHSR at TP using 350mm DI SAAP YEAR 2017-18 - this work arranged as a sub work of WTP. (3.) Transformer and Power line extension work executed through KSEB completed (4.) Construction of weir across Kallada River - The work retendered (Third) with due date on 26/2/22.Two bids recieved,PQ will be send to CEs office on 03-03-2022 STC. Is scheduled on 11/03/2022.(5.) Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed. (6.) 100 MLD - WTP - work in progress. 66% of work completed. (1) Cascade Aerator-– Pile cap works completed. Plinth beam at +4.50lvl completed. (2) Clariflocculators,(2.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl third lift completed . central shaft second lift completed. Inner base slab works of flocculator completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.b) CFL 2 - flocculator base slab Completed.Column up to 5.05lvl completed.ring beam works at 5.05 lvl in progress. pile chipping at outer area.Piling works completed.Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.c) CFL 3 - Piling works in progress (100% completed). Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.PCC for flocculator slab completed. flocculator baseslab completed. (3) Filter House-Columns up to 12.3m lvl slab completed.12.3m level slab casting (left side-Grid 6-9/A-M) completed. casting(part,grid 1-3/A-M) 40% completed.Remaining shuttering and rebar works in progress. Casting for columns above +12.3m lvl in progress. (4) Chemical House -Structural works completed Block work completed.(5) Admin Building-Foundation works completed. Plinth beam works completed. PCC for grade slab completed. RCC for grade slab completed. Casting for columns in progress. Over all 64 % of work completed. | Kollam Project Dn AE | |
| 01 Apr 2022 | I.)Construction of well completed . (2.) Clear Water Pumping main from WTP to 20LL OHSR at TP using 350mm DI SAAP YEAR 2017-18 - this work arranged as a sub work of WTP. (3.) Transformer and Power line extension work executed through KSEB completed (4.) Construction of weir across Kallada River - The work retendered (Third) with due date on 26/2/22.Two bids recieved,PQ will be send to CEs office on 03-03-2022 STC. Is scheduled on 11/03/2022.(5.) Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed. (6.) 100 MLD - WTP - work in progress. 66% of work completed. (1) Cascade Aerator-– Pile cap works completed. Plinth beam at +4.50lvl completed. (2) Clariflocculators,(2.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl third lift completed . central shaft second lift completed. Inner base slab works of flocculator completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.b) CFL 2 - flocculator base slab Completed.Column up to 5.05lvl completed.ring beam works at 5.05 lvl in progress. pile chipping at outer area.Piling works completed.Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.c) CFL 3 - Piling works in progress (100% completed). Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.PCC for flocculator slab completed. flocculator baseslab completed. (3) Filter House-Columns up to 12.3m lvl slab completed.12.3m level slab casting (left side-Grid 6-9/A-M) completed. casting(part,grid 1-3/A-M) 40% completed.Remaining shuttering and rebar works in progress. Casting for columns above +12.3m lvl in progress. (4) Chemical House -Structural works completed Block work completed.(5) Admin Building-Foundation works completed. Plinth beam works completed. PCC for grade slab completed. RCC for grade slab completed. Casting for columns in progress. Over all 64 % of work completed. | Kollam Project Dn AE | |
| 30 Mar 2022 | I.)Construction of well completed . (2.) Clear Water Pumping main from WTP to 20LL OHSR at TP using 350mm DI SAAP YEAR 2017-18 - this work arranged as a sub work of WTP. (3.) Transformer and Power line extension work executed through KSEB completed (4.) Construction of weir across Kallada River - The work retendered (Third) with due date on 26/2/22.Two bids recieved,PQ will be send to CEs office on 03-03-2022 STC. Is scheduled on 11/03/2022.(5.) Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed. (6.) 100 MLD - WTP - work in progress. 66% of work completed. (1) Cascade Aerator-– Pile cap works completed. Plinth beam at +4.50lvl completed. (2) Clariflocculators,(2.a) CFL 1 – Baffle walls from 5.5lvl to 9.05mlvl third lift completed . central shaft second lift completed. Inner base slab works of flocculator completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.b) CFL 2 - flocculator base slab Completed.Column up to 5.05lvl completed.ring beam works at 5.05 lvl in progress. pile chipping at outer area.Piling works completed.Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.(2.c) CFL 3 - Piling works in progress (100% completed). Cumulative pile casting 84 nos completed. Outer wall, inner wall, central shaft up to base slab levels completed.PCC for flocculator slab completed. flocculator baseslab completed. (3) Filter House-Columns up to 12.3m lvl slab completed.12.3m level slab casting (left side-Grid 6-9/A-M) completed. casting(part,grid 1-3/A-M) 40% completed.Remaining shuttering and rebar works in progress. Casting for columns above +12.3m lvl in progress. (4) Chemical House -Structural works completed Block work completed.(5) Admin Building-Foundation works completed. Plinth beam works completed. PCC for grade slab completed. RCC for grade slab completed. Casting for columns in progress. Over all 64 % of work completed. | Kollam Project Dn AE |