| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Feb 2021 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 100 % Completed (Except road restoration work at 1 km. Corporation road.This road included in PWD Budget work now it is in tender stage) . Shuttering and reinforcement work in progress for pile cap in chemical house area .PCC work in progress in filter house area. Foundation casting in sump pit. At Clarifoculator CFL1 boring 95 nos and casting 93 nos completed. At CFL2 boring 31 nos and casting 30 nos completed. Over all 42 % of work Completed. | Kollam Project HD | |
| 01 Feb 2021 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 97 % Completed (Except road restoration work at 1 km. Corporation road.This road included in PWD Budget work now it is in tender stage. Piling work of filter house completed (234 nos.) Excavation work for raft in progress. Chemical house piling work completed 25 nos. Boring & Casting of Clarriflocculator (CFL1) progressing (out of 181 nos. 47 nos. casted) . Site office and lab construction work finishing stage. Filter house pile load test in progress and Soil compaction of filter house work in Progress. Over all 42 % of Work Completed. | Kollam Project HD | |
| 11 Jan 2021 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 97 % Completed (Except road restoration work at 1 km. Corporation road.This road included in PWD Budget work now it is in tender stage. Piling work of filter house completed (234 nos.) Excavation work for raft in progress. Chemical house piling work completed 25 nos. Clarifoculator piling work is in progress. Overall 42 % of work completed. | Kollam Project HD | |
| 11 Jan 2021 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 97 % Completed (Except road restoration work at 1 km. Corporation road.This road included in PWD Budget work now it is in tender stage. Piling work of filter house completed (234 nos.) Excavation work for raft in progress. Chemical house piling work completed 25 nos. Clarifoculator piling work is in progress. Over all 43 % of work completed. | Kollam Project HD | |
| 11 Jan 2021 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 97 % Completed (Except road restoration work at 1 km. Corporation road.This road included in PWD Budget work now it is in tender stage. Piling work of filter house completed (234 nos.) Excavation work for raft in progress. Chemical house piling work completed 25 nos. Clarifoculator piling work is in progress. | Kollam Project HD | |
| 10 Dec 2020 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 90 % Completed. Road restoration works are in progress. pump house of Filter House out of 74 piles 5 Nos. of pile work completed, 2 Nos. of pile boring completed. reinforcement gauge for 20 piles completed. For chemical House Slushy soil removing work in Progress.Over all 41% of work completed. | Kollam Project HD | |
| 30 Nov 2020 | 15 CENT LAND ACQUIRED FOR CONSTRUCTION OF SUBSTATION BUILDING AND TRANSFORMER YARD.SUBSTATION BUILDING DESIGN SUBMITTED FOR VERIFICATION BY THE CONSULTANT.RETAINING WALL ESTIMATE PREPARED AND DESIGN OBTAINED FROM WASCON | Kollam Project HD | |
| 27 Nov 2020 | Construction of well completed . Laying of Clear water Pumping Main to Vadakkevila OHSR 89 % Completed. Gap closing work and Thrust block works are in progress. Dedicated power line extension to WTP and intake well amount deposited to KSEB, Work 95% completed. .Laying clear water pumping main to Vasoorichira OHSR Selection notice issued. Construction of weir across Kallada river executing through irrigation wing. Test pile work in progress. 100 MLD WTP - Design of Clarifoculators & filter house approved by WASCON, Structural Design of Chemical House, Administration Building, Aerator, Flash mixer etc verified and submitted to WASCON for approval. Site development works are completed, Testing of pile completed, Granular fill materials tested at CET TVM, Lay out of various units at progressing at site. Earth work of filter house in progressing. Over all 41% of work completed. | Kollam Project HD | |
| 26 Nov 2020 | Construction of well completed , Laying of Clear water Pumping Main to Vadakkevila OHSR 87 % Completed, Dedicated power line extension to WTP and intake well amount deposited to KSEB, Work 95% completed. Laying clear water pumping main to Vasoorichira OHSR Selection notice issued. Construction of weir across Kallada river executing through irrigation wing. 100 MLD WTP - Design of Clarifoculators & filter house approved by WASCON, Structural Design of Chemical House, Administration Building, Aerator, Flash mixer etc verified and submitted to WASCON for approval. Site development works are completed, Testing of pile completed, Granular fill materials tested at CET TVM, Lay out of various units at progressing at site. Earth work of filter house in progressing. Over all 41% of work completed | Kollam Project HD | |
| 17 Nov 2020 | Construction of well completed , Laying of Clear water Pumping Main to Vadakkevila OHSR 87 % Completed, Dedicated power line extension to WTP and intake wll amount deposited to KSEB, Work 95% completed.Laying clear water pumping main to Vasoorichira OHSR Selection notice issued.Construction of weir across Kallada river executing through irrigation wing. Over all 40% of work completed | Kollam Project HD |