Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Feb 2024 | 10 th and Part bill submitted. (1268 connections completed out of 2300 (693 HTCs and 575 FHTCs) | Vadanappilly AE | |
21 Feb 2024 | 9 th and Part bill submitted. (1268 connections completed out of 2300 (693 HTCs and 575 FHTCs) | Vadanappilly AE | |
14 Feb 2024 | 9 th and Part bill submitted. (1268 connections completed out of 2300 (693 HTCs and 575 FHTCs) | Vadanappilly AE | |
06 Feb 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 (596 HTCs and 575 FHTCs) | Vadanappilly AE | |
25 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
22 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
17 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
11 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
08 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
03 Jan 2024 | 9 th and Part bill submitted. (1171 connections completed out of 2300 ( 596 HTCs and 575 FHTCs) | Vadanappilly AE |