Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs). | Vadanappilly AE | |
27 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
24 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
20 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
18 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
13 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
10 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
06 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
03 Jul 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
29 Jun 2023 | 9 th and Part bill submitted.(1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE |