Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab concrete completed at Parakkunnam OSHR. Roof slab centering and shuttering work completed in Perumparamb OSHR. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 610 FHTC and 485 HTC given. Perinthalmanna AE
14 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab shuttering and centering work going on in both perumbarambu and parakkunnam tank. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 610 FHTC and 485 HTC given. Perinthalmanna AE
10 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 610 FHTC and 485 HTC given. Perinthalmanna AE
06 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 587 FHTC and 485 HTC given. Perinthalmanna AE
04 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 567 FHTC and 485 HTC given. Perinthalmanna AE
02 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 541 FHTC and 485 HTC given. Perinthalmanna AE
30 Jan 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 530 FHTC and 462 HTC given. Perinthalmanna AE
27 Jan 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 521 FHTC and 451 HTC given. Perinthalmanna AE
21 Jan 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR.Side wall third lift of 0.8m concreting completed for both OHSRs. Remaining side wall shuttering and reinforcement works ongoing, 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 521 FHTC and 451 HTC given. Perinthalmanna AE
17 Jan 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR.Side wall third lift of 0.8m concreting completed for both OHSRs. Remaining side wall shuttering and reinforcement works ongoing, 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 521 FHTC and 451 HTC given. Perinthalmanna AE