Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering work going on. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 787 FHTC and 421HTC given.608 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
17 Mar 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering work going on. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 787 FHTC and 421HTC given.608 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
13 Mar 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 744 FHTC and 459HTC given.608 FHTC Bill submitted and 470 HTC bill submitted. Both tanks plastering work going on. Perinthalmanna AE
11 Mar 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 686 FHTC and 514 HTC given.608 FHTC Bill submitted and 470 HTC bill submitted. Both tanks plastering work going on. Perinthalmanna AE
09 Mar 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 682 FHTC and 479 HTC given.608 FHTC Bill submitted and 470 HTC bill submitted. Both tanks plastering work going on. Perinthalmanna AE
07 Mar 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 682 FHTC and 479 HTC given.608 FHTC Bill submitted and 470 HTC bill submitted Perinthalmanna AE
06 Mar 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 682 FHTC and 479 HTC given.608 FHTC Bill submitted and 470 HTC bill submitted Perinthalmanna AE
28 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 612 FHTC and 484 HTC given.608 FHTC Bill submitted and 470 HTC bill submitted Perinthalmanna AE
25 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab and stair concrete completed at both OHSRs. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 612 FHTC and 485 HTC given. Perinthalmanna AE
21 Feb 2023 Floor slab and haunch concreting completed for both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR. Side wall concrete completed upto 3.6m for both OHSRs. Roof slab concrete completed at Parakkunnam OSHR. Roof slab centering and shuttering work completed in Perumparamb OSHR. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 610 FHTC and 485 HTC given. Perinthalmanna AE