Status Date Overall Project Status Project Officer Contact
20 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
19 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
14 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
12 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
08 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
07 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
05 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
03 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1306 FHTC and 408 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
01 Jun 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1236 FHTC and 430 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE
29 May 2023 Both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. Valve chamber work ongoing. 250mm DI 822.5m laid, 160mmPE 988.5m laid, 90mm PE 14503.1m laid, 1236 FHTC and 430 HTC given.889 FHTC Bill submitted and 470 HTC bill submitted. Perinthalmanna AE