Jal Jeevan Mission - 2021-22 - Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2

Project Jal Jeevan Mission - 2021-22 - Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2
Project Code MLPJJM09219076
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction of OHSR 8LL, VALVE CHAMBER, FHTCs -2000nos, tank -inter connection works, compound wall, OH Tank 2.25ll pump set, design and survey of new distribution lines
Status On-going
District Malappuram
Executing Office Malappuram PH Dn
AS Amount (Rs) 151900000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 151100000
TS Number Reg .No. 15525/2021-2022
Total Bill Submitted (Rs) 28936382
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 0.00
Actual Project Completion Date Date is not specified
Coverage 2000FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- 2021-22- Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2 Perinthalmanna PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2024 both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. Perinthalmanna AE
15 Jun 2024 both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. Perinthalmanna AE
10 Jun 2024 both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. Perinthalmanna AE
06 Jun 2024 both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. Perinthalmanna AE
28 May 2024 both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. Perinthalmanna AE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
03 Oct 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) Elamkulam Grama panchayath PMGSY road with DLP Earlier during estimate preparation stage,we considered it as a normal GP road. Recently only we identified it as a DLP PMGSY road.We applied foe permission for cutting (bitumin cutting for less than 100m ). Demand of 35 lakhs given to us,but when consiidering the pipe alignment route this amount is high.Hence requested for further deduction.They agreed for re inspection on 23/10/2022. No comments available. Pending

Duration & Sanction dates

Date of start of Project 05/04/2022
Scheduled date of Completion of the Project 21 Jan 2023
Expected date of Completion 21/01/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 16 Dec 2021

Other details

Project Officers View