Jal Jeevan Mission - 2021-22 - Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2
Project |
Jal Jeevan Mission - 2021-22 - Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2 |
Project Code |
MLPJJM09219076 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction of OHSR 8LL,
VALVE CHAMBER,
FHTCs -2000nos,
tank -inter connection works,
compound wall,
OH Tank 2.25ll
pump set,
design and survey of new distribution lines |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
151900000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
151100000 |
TS Number |
Reg .No. 15525/2021-2022 |
Total Bill Submitted (Rs) |
28936382 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
2000FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission- 2021-22- Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2 |
Perinthalmanna PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. |
Perinthalmanna AE |
|
15 Jun 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. |
Perinthalmanna AE |
|
10 Jun 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. |
Perinthalmanna AE |
|
06 Jun 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. |
Perinthalmanna AE |
|
28 May 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1866 FHTC and 432HTC given.construction of valve chamber completed. |
Perinthalmanna AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
03 Oct 2022 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Elamkulam Grama panchayath
PMGSY road with DLP
Earlier during estimate preparation stage,we considered it as a normal GP road. Recently only we identified it as a DLP PMGSY road.We applied foe permission for cutting (bitumin cutting for less than 100m ). Demand of 35 lakhs given to us,but when consiidering the pipe alignment route this amount is high.Hence requested for further deduction.They agreed for re inspection on 23/10/2022. |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
05/04/2022 |
Scheduled date of Completion of the Project |
21 Jan 2023 |
Expected date of Completion |
21/01/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
16 Dec 2021 |