Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Apr 2024 |
Work in progress | 9% Completed | 19/04/2024
. 90MM Pipe laid for a length of 13 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-3904m 2)PVC 8 kg-5040m 3.110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|
11 Apr 2024 |
Work in progress | 9% Completed | 11/04/2024
Pipe laid for a length of 12.686 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-3690m 2. 90MM PVC 8 kg-5040m 3.110 mm pvc 10 kg-1158m |
Chittur Project Dn - AE 3 |
|
30 Mar 2024 |
Work in progress | 8% Completed | 30/03/2024
Pipe laid for a length of 11.804 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-2970m 2. 90MM PVC 8 kg-4878m 3.110 mm pvc 10 kg-1158m |
Chittur Project Dn - AE 3 |
|
21 Mar 2024 |
Work in progress | 6% Completed | 21/03/2024
Pipe laid for a length of 9.068 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-2832m 2. 90MM PVC 8 kg-2280m 3.110 mm pvc 10 kg-1158m |
Chittur Project Dn - AE 3 |
|
13 Mar 2024 |
Work in progress | 6% Completed | 13/03/2024
Pipe laid for a length of 8.294 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-2388m 2. 90MM PVC 8 kg-1950m 3.110 mm pvc 10 kg-1158m |
Chittur Project Dn - AE 3 |
|
06 Mar 2024 |
Work in progress | 4% Completed | 06/03/2024
Pipe laid for a length of 6.33 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-1788m 2. 90MM PVC 8 kg-1128m 3.110 mm pvc 10 kg-612m |
Chittur Project Dn - AE 3 |
|
28 Feb 2024 |
Pipe laid for a length of -4.704 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-1320m 2. 90MM PVC 8 kg-222m 3.110 mm pvc 10 kg-360m |
Chittur Project Dn - AE 3 |
|
22 Feb 2024 |
Pipe laid for a length of -2.802 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-1926m 2. 90MM PVC 8 kg-876m |
Chittur Project Dn - AE 3 |
|
14 Feb 2024 |
Work in progress | 1% Completed | 14/02/2024
Pipe laid for a length of -1.068 KM /150km,(total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-720m 2. 90MM PVC 8 kg-348m |
Chittur Project Dn - AE 3 |
|
24 Jan 2024 |
pipe supply work in progress |
Chittur Project Dn - AE 1 |
|