Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
22 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
17 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
14 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
10 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
06 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
02 Mar 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
26 Feb 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
22 Feb 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
18 Feb 2022 | 2299 Nos FHTCS provided and 27.8km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted | Perlassery Sn 2 AE |