Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Jan 2022 | 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
18 Jan 2022 | 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
13 Jan 2022 | 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
10 Jan 2022 | 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
06 Jan 2022 | 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
02 Jan 2022 | 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
29 Dec 2021 | 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
24 Dec 2021 | 2121 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
20 Dec 2021 | 2120 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2040 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
16 Dec 2021 | 2114 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2040 nos FHTCS bill submitted | Perlassery Sn 2 AE |