Status Date Overall Project Status Project Officer Contact
21 Jan 2022 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
18 Jan 2022 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
13 Jan 2022 2166 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
10 Jan 2022 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
06 Jan 2022 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
02 Jan 2022 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
29 Dec 2021 2137 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
24 Dec 2021 2121 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2115 nos FHTCS bill submitted Perlassery Sn 2 AE
20 Dec 2021 2120 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2040 nos FHTCS bill submitted Perlassery Sn 2 AE
16 Dec 2021 2114 Nos FHTCS provided and 27km pipe line extended Physical progress 73 %. Pipe supply, 24.8 km laying and 2040 nos FHTCS bill submitted Perlassery Sn 2 AE