Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
20 Jun 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
18 Jun 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
10 Jun 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
01 Jun 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
22 May 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
17 May 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
08 May 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
25 Apr 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
18 Apr 2024 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE