Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Sep 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
19 Sep 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
11 Sep 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
09 Sep 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
03 Sep 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
30 Aug 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
26 Aug 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
22 Aug 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
19 Aug 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE | |
13 Aug 2022 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted | Perlassery Sn 2 AE |