Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
27 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
19 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
14 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
10 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
04 Jul 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
30 Jun 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
24 Jun 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
19 Jun 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE | |
16 Jun 2023 | 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged | Perlassery Sn 2 AE |