Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Oct 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
03 Oct 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
27 Sep 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
21 Sep 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
13 Sep 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
01 Sep 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
24 Aug 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Perlassery Sn 2 AE
17 Aug 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged. Kannur PH Dn EE
09 Aug 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged Perlassery Sn 2 AE
04 Aug 2023 2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 nos FHTCS bill submitted Remaining bill submitted-Balance work arranged Perlassery Sn 2 AE