Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Oct 2023 | Thevancode ward Total pipe 75 mm pvc = 60m #Thevancode ward Total pipe 90 mm pvc = 90m #kallikadu ward Connection = 3nos | Neyyattinkara WS Dn EE | |
07 Oct 2023 | Thevancode ward Total pipe 75 mm pvc =330m | Neyyattinkara WS Dn EE | |
06 Oct 2023 | Thevancode ward Total pipe 75 mm pvc = 150m #Thevancode ward Total pipe 90 mm pvc = 84m | Neyyattinkara WS Dn EE | |
05 Oct 2023 | ongoing | Neyyattinkara WS Dn EE | |
04 Oct 2023 | Kallikadu grama panchayat JJM Third face Work starting Paruthi pally Thuranna Jail Road 90mm pvc 8.kg 2526m laid | Neyyattinkara WS Dn EE |