Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Dec 2023 Aduvally # kalipara Total pipe 160mm 150m Total pipe 110mm 60m Neyyattinkara WS Dn EE
26 Dec 2023 Aduvally # kalipara Total pipe 160mm 240m Neyyattinkara WS Dn EE
22 Dec 2023 Aduvally # kalipara Total pipe 160mm 48m Total pipe 110mm 48m Kattakkada WS Sn AE
21 Dec 2023 Aduvally # kalipara Total pipe 160mm 36m Total pipe 110mm 36m Kattakkada WS Sn AE
19 Dec 2023 Aduvally # kalipara Total pipe 160mm 48m Total pipe 110mm 48m Kattakkada WS Sn AE
18 Dec 2023 Aduvally # kalipara Total pipe 160mm 36m Total pipe 110mm 36m Kattakkada WS Sn AE
16 Dec 2023 Aduvally # kalipara Total pipe 160mm 120m Total pipe 110mm 126m Neyyattinkara WS Dn EE
13 Dec 2023 Aduvally # kalipara Total pipe 160mm 48m Total pipe 110mm 48m Neyyattinkara WS Dn EE
12 Dec 2023 Aduvally # kalipara Total pipe 160mm 36m Total pipe 110mm 36m Neyyattinkara WS Dn EE
11 Dec 2023 Aduvally # kalipara Total pipe 160mm 48m Total pipe 110mm 48m Neyyattinkara WS Dn EE