Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Nov 2023 | kallikadu ward-Total connection - 3 | Neyyattinkara WS Dn EE | |
03 Nov 2023 | Thevancode ward Total pipe 90 mm pvc =84m Depth=1m | Neyyattinkara WS Dn EE | |
02 Nov 2023 | Thevancode ward Total pipe 90 mm pvc =162m Depth=1m | Neyyattinkara WS Dn EE | |
01 Nov 2023 | Thevancode ward Total pipe 90 mm pvc =174m Depth=1m | Neyyattinkara WS Dn EE | |
31 Oct 2023 | Thevancode ward Total pipe 90 mm pvc =234 m Depth=1m | Neyyattinkara WS Dn EE | |
30 Oct 2023 | Thevancode ward Total pipe 90 mm pvc = 180m | Neyyattinkara WS Dn EE | |
28 Oct 2023 | ON GOING | Neyyattinkara WS Dn EE | |
26 Oct 2023 | kallikadu ward Total connection - 1 #manchali moodu ward Total connection -2 | Neyyattinkara WS Dn EE | |
25 Oct 2023 | ongoing | Neyyattinkara WS Dn EE | |
24 Oct 2023 | ongoing | Neyyattinkara WS Dn EE |