Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Jun 2022 | 1526FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
02 Jun 2022 | 1526FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
30 May 2022 | 1526FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
27 May 2022 | 1526FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
23 May 2022 | 1526FHTCs completed out of 4400, 12th and part bill submitted, work stopped due to shortage of pipe | Vadanappilly AE | |
20 May 2022 | 1515FHTCs completed out of 4400, 12th and part bill submitted, work stopped due to shortage of pipe | Vadanappilly AE | |
19 May 2022 | 1515FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
16 May 2022 | 1515FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
12 May 2022 | 1510 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
10 May 2022 | 1510 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE |