Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Oct 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted. | Vadanappilly AE | |
27 Oct 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted. | Vadanappilly AE | |
25 Oct 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted. | Vadanappilly AE | |
20 Oct 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted.350mm DI Pipes laid in trench from kothakulam to Disco center | Vadanappilly AE | |
17 Oct 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted.350mm DI Pipes laid in trench from kothakulam to Disco center | Vadanappilly AE | |
19 Sep 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
13 Sep 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
05 Sep 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
03 Sep 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE | |
29 Aug 2022 | 1540 FHTCs completed out of 4400, 12th and part bill submitted | Vadanappilly AE |