| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Oct 2024 | Excavation for main chamber nearby tank | Kadakkal PH Sn - AE | |
| 27 Oct 2024 | Providing roof Slab for chamber | Kadakkal PH Sn - AE | |
| 23 Oct 2024 | Chamber construction | Kadakkal PH Sn - AE | |
| 11 Oct 2024 | Concreting | Kadakkal PH Sn - AE | |
| 10 Oct 2024 | Laying reinforcement for chamber | Kadakkal PH Sn - AE | |
| 09 Oct 2024 | Shuttering work for chamber | Kadakkal PH Sn - AE | |
| 08 Oct 2024 | Earthwork excavation for 6 chambers | Kadakkal PH Sn - AE | |
| 14 Oct 2024 | Same Status | Kadakkal PH Sn - AE | |
| 07 Oct 2024 | Same Status | Kadakkal PH Sn - AE | |
| 03 Oct 2024 | Same Status | Kadakkal PH Sn - AE |