| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Dec 2024 | Same status | Kadakkal PH Sn - AE | |
| 16 Dec 2024 | Same status | Kadakkal PH Sn - AE | |
| 09 Dec 2024 | Same Status | Kadakkal PH Sn - AE | |
| 26 Nov 2024 | water filled in tank | Kadakkal PH Sn - AE | |
| 25 Nov 2024 | chamber construction for main valve | Kadakkal PH Sn - AE | |
| 21 Nov 2024 | Same Status | Kadakkal PH Sn - AE | |
| 11 Nov 2024 | Main Valve Fixing | Kadakkal PH Sn - AE | |
| 07 Nov 2024 | Fixing of main valves | Kadakkal PH Sn - AE | |
| 06 Nov 2024 | Same Status | Kadakkal PH Sn - AE | |
| 01 Nov 2024 | Same Status | Kadakkal PH Sn - AE |